Deposit Work-TSS-Mace-Running Contract 2020-2021-Rectification of blockages, Cleaning the sewer line, Repair of water supply arrangements and allied works in Super Speciality Block, Multi Speciality Block of Medical College for the year 2020-2021.
| Project |
Deposit Work-TSS-Mace-Running Contract 2020-2021-Rectification of blockages, Cleaning the sewer line, Repair of water supply arrangements and allied works in Super Speciality Block, Multi Speciality Block of Medical College for the year 2020-2021. |
| Project Code |
TVMGOK08206041P1 |
| Type |
Package |
| Main Project |
Deposit Work-2020-21-KWA Medical college
|
| Funding Agency |
GOK |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
Deposit Work-TSS-Mace-Running Contract 2020-2021-Rectification of blockages, Cleaning the sewer line, Repair of water supply arrangements and allied works in Super Speciality Block, Multi Speciality Block of Medical College for the year 2020-2021. |
| Status |
On-going |
| District |
Thiruvananthapuram |
| Executing Office |
TVM Medical College Sn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
1059000 |
| TS Number |
14566/2020-2021 |
| Technical specification |
Rectification of blockages, Cleaning the sewer line, Repair of water supply arrangements and allied works in Super Speciality Block, Multi Speciality Block of Medical College for the year 2020-2021. |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
08/02/2021 |
| Scheduled date of Completion as per agreement |
07 Feb 2022 |
| Expected date of Completion |
31/03/2022 |
Processing Dates
| TS Date |
14 Jan 2021 |
| Estimate Approval |
14 Jan 2021 |
| NIT Approval |
18 Jan 2021 |
| Tender Closing |
29 Jan 2021 |
| Price bid opening |
02 Feb 2021 |
Approval Dates
| Workorder Date |
08 Feb 2021 |
| NA |
18 Feb 2021 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Thiruvananthapuram - Med col - AE |
| Date: 27/04/2022 |
Work has been completed | 100% Completed
Running Contract completed for the year 2020-2021.
| Thiruvananthapuram - Med col - AE |
| Date: 25/04/2022 |
Work has been completed | 100% Completed
Running Contract completed for the year 2020-2021.