AMRUT-2016-17-Zoning & Mapping of WSS to Thrissur Corporation-Supply and laying of various Dia Pipe- Part I (Revised AS - 8.52 Cr)
Project |
AMRUT-2016-17-Zoning & Mapping of WSS to Thrissur Corporation-Supply and laying of various Dia Pipe- Part I (Revised AS - 8.52 Cr) |
Project Code |
TCRGOI0118534 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Transmission main-1000mm to 200mmDI-6.979km |
Status |
Completed |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
85200000
|
AS Number |
Go(Rt)No.1951/2021/LSGD |
TS Amount (Rs) |
80000000 |
TS Number |
AS No - G.O(Rt) No.5/2018/LSGD dt.01.01.2018 |
Total Bill Submitted (Rs) |
65906818 |
Total Bill Paid (Rs) |
65820026 |
Population Benefitted |
395436 |
Capacity in MLD |
26.30 |
Actual Project Completion Date |
18 Aug 2020 |
Coverage |
This project is intended to ensure adequate drinking water facility for Zone 1 ( Kokkala, Koorkenchery) and Zone 2 (Pallikkulam, Kannankulangara) of Thrissur Corporation. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT- Zoning and mapping (Part1) -Supply and laying of various Dia Pipes-6.979km |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
23 Aug 2022 |
Completed |
Nattika Project Dn |
|
13 Jun 2022 |
All works completed. energisation of flow meter pending. |
Nattika Project Dn |
|
04 Jun 2022 |
All works completed. energisation of flow meter pending. |
Nattika Project Dn |
|
04 Jun 2022 |
All works completed. energisation of flow meter pending. |
Nattika Project Dn |
|
03 Jun 2022 |
All works completed. energisation of flow meter pending. |
Nattika Project Dn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/02/2019 |
Scheduled date of Completion of the Project |
09 Dec 2019 |
Expected date of Completion |
18/08/2020 |
Processing Dates
AS Date |
08 Oct 2021 |
TS Date |
29 Jan 2018 |