- Jal Jeevan Mission -Peringotukurissi-Pha...
Jal Jeevan Mission -Peringotukurissi-Phase-IV-Balance Pipelaying through Nariyalakundu Forest Land and Road restoration of LSGD roads ( JJM Balance Work Peringottukurissi Panchayath)
Project |
Jal Jeevan Mission -Peringotukurissi-Phase-IV-Balance Pipelaying through Nariyalakundu Forest Land and Road restoration of LSGD roads ( JJM Balance Work Peringottukurissi Panchayath) |
Project Code |
PKDJJM042215386 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission-Peringotukurissi-Phase-IV-Balance Pipelaying through Nariyalakundu Forest Land and Road restoration
of LSGD roads ( JJM Balance Work Peringottukurissi Panchayath) |
Status |
On-going |
District |
Palakkad |
Executing Office |
Kuzhalmannam Sn |
AS Amount (Rs) |
51731000
|
AS Number |
G.O.(RT)No.134/2022/WRD |
TS Amount (Rs) |
9840000 |
TS Number |
TS/21253/2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
700 |
Capacity in MLD |
6.00 |
Actual Project Completion Date |
28 May 2024 |
Coverage |
Peringottukurissi Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission -Peringotukurissi-Phase-IV-Balance Pipelaying through Nariyalakundu Forest Land and Road restoration of LSGD roads ( JJM Balance Work Peringottukurissi Panchayath) |
Kuzhalmannam Sn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
28/11/2023 |
Scheduled date of Completion of the Project |
28 May 2024 |
Expected date of Completion |
28/05/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
06 Nov 2023 |