Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit work- IWAI-CWSS to Oachira,Clappana,Alappad and karunagappally- Providing water supply connection to IWT terminal at Ayiramthengu

Project Deposit work- IWAI-CWSS to Oachira,Clappana,Alappad and karunagappally- Providing water supply connection to IWT terminal at Ayiramthengu
Project Code KLMDEPO072212393
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work- IWAI-CWSS to Oachira,Clappana,Alappad and karunagappally- Providing water supply connection to IWT terminal at Ayiramthengu
Status Completed
District Kollam
Executing Office Chavara PH Sub Dn
AS Amount (Rs) 25400
AS Number IWAI/COCFI/49/O&M(1)/41SCI 1021-2221 1
TS Amount (Rs) 25400
TS Number 11225/2022-23
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 10
Capacity in MLD 0.00
Actual Project Completion Date Date is not specified
Coverage IWT terminal at Ayiramthengu
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work- IWAI-CWSS to Oachira,Clappana,Alappad and karunagappally- Providing water supply connection to IWT terminal at Ayiramthengu Oachira PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Dec 2022 Work Completed Oachira AE
08 Dec 2022 Work Completed Oachira AE
30 Nov 2022 Work Completed Oachira AE
26 Nov 2022 Connection process ongoing through etapp Oachira AE
26 Nov 2022 Connection process ongoing through etapp Kollam PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/09/2022
Scheduled date of Completion of the Project 04 Oct 2022
Expected date of Completion 30/11/2022

Processing Dates

AS Date 11 Jul 2022
TS Date 26 Jul 2022

Other details

Project Officers View