DEPOSIT-ANNUAL PLAN 2021-2022-ARATTUPUZHA GRAMA PANCHAYATH CONSTRUCTION OF PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY AND ERECTION OF PUMPSET AND COMMISSIONING OF NEW TUBE WELL NEAR THARAYILKKADAVU IN WARD 7 OF ARATTUPUZHAGRAMA PANCHAYATH

Project DEPOSIT-ANNUAL PLAN 2021-2022-ARATTUPUZHA GRAMA PANCHAYATH CONSTRUCTION OF PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY AND ERECTION OF PUMPSET AND COMMISSIONING OF NEW TUBE WELL NEAR THARAYILKKADAVU IN WARD 7 OF ARATTUPUZHAGRAMA PANCHAYATH
Project Code ALPDEPO022415767P1
Type Package
Main Project DEPOSIT-ANNUAL PLAN 2021-2022-ARATTUPUZHA GRAMA PANCHAYATH CONSTRUCTION OF PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY AND ERECTION OF PUMPSET AND COMMISSIONING OF NEW TUBE WELL NEAR THARAYILKKADAVU IN WARD 7 OF ARATTUPUZHAGRAMA PANCHAYATH
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description CONSTRUCTION OF PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY AND ERECTION OF PUMPSET AND COMMISSIONING OF NEW TUBE WELL NEAR THARAYILKKADAVU IN WARD 7 OF ARATTUPUZHAGRAMA PANCHAYATH
Status On-going
District Alappuzha
Executing Office Kayamkulam PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 723000
TS Number WRD/KWA-CE(CR)/EST_TS/920/2024_26_1_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/03/2024
Scheduled date of Completion as per agreement 12 Aug 2024
Expected date of Completion 12/08/2024

Processing Dates

TS Date 21 Feb 2024
Estimate Approval 20 Feb 2024
NIT Approval 22 Feb 2024
Tender Closing 05 Mar 2024
Price bid opening 06 Mar 2024

Approval Dates

Workorder Date 12 Mar 2024
NA 13 Mar 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kayamkulam AE
Date: 07/05/2024

Work in progress | 30% Completed

CONSTRUCTION OF PUMP HOUSE COMPLETED.

Kayamkulam AE
Date: 02/05/2024

Work in progress | 30% Completed

CONSTRUCTION OF PUMP HOUSE COMPLETED.