- Home
- Deposit work - Nagar Sanjayam - WSS to U...
Deposit work - Nagar Sanjayam - WSS to Ullanam North in Parappanangadi Muncipality , Malappuram District - Construction of OHSR OF 3 Lakhs Liters Capacity , 250mm DI Pumping main , Installation of Pressure filter ,Distribution network and allied works
Project |
Deposit work - Nagar Sanjayam - WSS to Ullanam North in Parappanangadi Muncipality , Malappuram District - Construction of OHSR OF 3 Lakhs Liters Capacity , 250mm DI Pumping main , Installation of Pressure filter ,Distribution network and allied works |
Project Code |
MLPDEPO112214595 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Construction of OH Tank ,Laying Pumping main, Construction of valve chambers,Row water pump set - 60HP |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram PH Dn |
AS Amount (Rs) |
50000000
|
AS Number |
A2/15893/2022 |
TS Amount (Rs) |
50000000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/4039/2022_12_1_1 |
Total Bill Submitted (Rs) |
6766543 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
10000 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Construction of OH Tank ,Laying Pumping main, Construction of valve chambers,Row water pump set - 60HP |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work - Nagar Sanjayam - WSS to Ullanam North in Parappanangadi Muncipality , Malappuram District - Construction of OHSR OF 3 Lakhs Liters Capacity , 250mm DI Pumping main , Installation of Pressure filter ,Distribution network and allied works |
Parappanangadi PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Apr 2024 |
OHSR work 95% completed. Distribution pipeline 85 % completed |
Malappuram PH Dn EE |
|
14 Feb 2024 |
OHSR work 95% completed. Distribution pipeline 80 % completed |
Malappuram PH Dn EE |
|
03 Feb 2024 |
OHSR work 85% completed. Distribution pipeline 80 % completed |
Malappuram PH Dn EE |
|
03 Feb 2024 |
OHSR work 85% completed. Distribution pipeline 80 % completed. |
Malappuram PH Dn EE |
|
16 Jan 2024 |
OHSR work 85% completed. Distribution pipeline 75% completed. |
Malappuram PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/02/2023 |
Scheduled date of Completion of the Project |
24 Feb 2024 |
Expected date of Completion |
24/02/2024 |
Processing Dates
AS Date |
15 Nov 2022 |
TS Date |
23 Dec 2022 |