Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part II-Pipeline work |
---|---|
Project Code | KNRAMRUT122315864P1 |
Type | Package |
Main Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part II-Pipeline work |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part II-Pipeline work |
Status | On-going |
District | Kannur |
Executing Office | Kannur WS Sn 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 33000000 |
TS Number | 23559/2023-24 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 29/02/2024 |
---|---|
Scheduled date of Completion as per agreement | 18 Apr 2024 |
Expected date of Completion | 18/04/2024 |
TS Date | 06 Jan 2024 |
---|---|
NIT Approval | 08 Jan 2024 |
Tender Closing | 15 Jan 2024 |
Price bid opening | 16 Jan 2024 |
Workorder Date | 05 Feb 2024 |
---|---|
NA | 19 Feb 2024 |
Kannur WS Sn AE 2 |
Date: 03/07/2025 |
Work in progress | 95% Completed
Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, Final bill sumbitted..
Kannur WS Sn AE 2 |
Date: 30/06/2025 |
Work in progress | 95% Completed
Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, Final bill sumbitted..