- Home
- AMRUT - 2.0 - UWSS Ottapalam -Augmentati...
AMRUT - 2.0 - UWSS Ottapalam -Augmentation of Urban Water Supply Scheme to Ottappalam Municipality- Supplying and Laying Distribution System,Providing FHTCs,Rennovation of Existing 13 MLD Water Treatment Plant,Rennovation to OHSRs,GLSRs, Office building & Supply,Erection and Commissioning of Motor Pump Set at Clear Water Pump House
Project |
AMRUT - 2.0 - UWSS Ottapalam -Augmentation of Urban Water Supply Scheme to Ottappalam Municipality- Supplying and Laying Distribution System,Providing FHTCs,Rennovation of Existing 13 MLD Water Treatment Plant,Rennovation to OHSRs,GLSRs, Office building & Supply,Erection and Commissioning of Motor Pump Set at Clear Water Pump House |
Project Code |
PKDAMRUT2112212864 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
|
Description |
AMRUT - 2.0 - UWSS Ottapalam -Augmentation of Urban Water Supply Scheme to Ottappalam Municipality- Supplying and Laying Distribution System,Providing FHTCs,Rennovation of Existing 13 MLD Water Treatment Plant,Rennovation to OHSRs,GLSRs, Office building & Supply,Erection and Commissioning of Motor Pump Set at Clear Water Pump House |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
107500000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
103400000 |
TS Number |
WRD/KWA-CE NR/EST TS/1301/2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
62205 |
Capacity in MLD |
13.00 |
Actual Project Completion Date |
18 Jul 2024 |
Coverage |
Water Supply Scheme to Ottappalam Municipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-2.0 – Ottapalam municipality - Relaying the raw water pumping main across railway track 50m length, 500mm MS Carrier pipe in between Palappuram -Ottapalam railway stations |
Ottappalam PH Sn |
|
2 |
AMRUT - UWSS to Ottapalam Municipality - Providing new pipe line and FHTCs, Renovation of existing OHSRs, GSLRs, Office building, Toilet and a store at RWPH - Reach 2 |
Ottappalam PH Sn |
|
3 |
AMRUT -UWSS to Ottapalam Municipality - Replacing old pipe line, Providing New pipe line extension and FHTCs in Ottapalam Municipality - Reach 1 |
Ottappalam PH Sn |
|
4 |
AMRUT -UWSS to Ottapalam Municipality - Supply and Errection of Motor pump set and providing new pipe lines - Reach 3 |
Ottappalam PH Sn |
|
5 |
UWSS to Ottapalam Municipality - Providing FHTCs and Pipe line extention Reach 4 |
Ottappalam PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Feb 2024 |
Work order issued on 11/10/2023 & agreement executed. Third party inspection of PVC pipes arranged on 12/12/2023. Pipe supplied by the Contractor. CC 1st and Part bill submitted. PVC Pipe laying work almost completed. Connection shifting and interconnection work in progress. |
Shornur PH Dn EE |
|
13 Nov 2023 |
Tendered 4 times. Nobody quoted. Estimate recast into 5 packages Package I railway crossing work arranged (31 L) Package II Reach 1(2.40 Cr) Estimate returned to AE for submitting for TS Package III Reach 2(2.40 Cr)Estimate returned to AE for submitting for TS Package IV Reach 3(1.64 Cr) Estimate submitted for OD sanction to CE on 5.6.23 Package V Reach 4(2.55 Cr) Estimate submitted to CE on 5.06.23 |
Ottappalam PH Sn AE |
|
08 Sep 2023 |
Tendered 4 times. Nobody quoted. Estimate recast into 5 packages Package I railway crossing work arranged (31 L) Package II Reach 1(2.40 Cr) Estimate returned to AE for submitting for TS Package III Reach 2(2.40 Cr)Estimate returned to AE for submitting for TS Package IV Reach 3(1.64 Cr) Estimate submitted for OD sanction to CE on 5.6.23 Package V Reach 4(2.55 Cr) Estimate submitted to CE on 5.06.23 |
Ottappalam PH Sn AE |
|
08 Sep 2023 |
Tendered 4 times. Nobody quoted. Estimate recast into 5 packages Package I railway crossing work arranged (31 L) Package II Reach 1(2.40 Cr) Estimate returned to AE for submitting for TS Package III Reach 2(2.40 Cr)Estimate returned to AE for submitting for TS Package IV Reach 3(1.64 Cr) Estimate submitted for OD sanction to CE on 5.6.23 Package V Reach 4(2.55 Cr) Estimate submitted to CE on 5.06.23 |
Ottappalam PH Sn AE |
|
21 Jun 2023 |
Tendered 4 times. Nobody quoted. Estimate recast into 5 packages Package I railway crossing work arranged (31 L) Package II Reach 1(2.40 Cr) Estimate returned to AE for submitting for TS Package III Reach 2(2.40 Cr)Estimate returned to AE for submitting for TS Package IV Reach 3(1.64 Cr) Estimate submitted for OD sanction to CE on 5.6.23 Package V Reach 4(2.55 Cr) Estimate submitted to CE on 5.06.23 |
Ottappalam PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
27/06/2023 |
Scheduled date of Completion of the Project |
18 Jul 2024 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
31 Jan 2023 |