DEPOSIT-Kodakara Block Panchayath-WSS to Nayattukundu Mattathur Grama pt.-Supply and laying of pumping main and distribution line, Construction of Ferrocement Pump house Construction of OHSR at Nayattukundu Mattathur Grammapanchayat

Project DEPOSIT-Kodakara Block Panchayath-WSS to Nayattukundu Mattathur Grama pt.-Supply and laying of pumping main and distribution line, Construction of Ferrocement Pump house Construction of OHSR at Nayattukundu Mattathur Grammapanchayat
Project Code TCRDEPO022415693
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Kodakara Block Panchayath-WSS to Nayattukundu Mattathur Grama pt.-Supply and laying of pumping main and distribution line, Construction of Ferrocement Pump house Construction of OHSR at Nayattukundu Mattathur Grammapanchayat
Status On-going
District Thrissur
Executing Office Chalakkudy PH Sn
AS Amount (Rs) 2000000
AS Number BOKDA/121/2023-D
TS Amount (Rs) 2000000
TS Number WRD/KWA-CE(CR)/EST_TS/7399/2023_5_1_1 Dated: 01-03-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 40
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 DEPOSIT-Kodakara Block Panchayath-WSS to Nayattukundu Mattathur Grama pt.-Supply and laying of pumping main and distribution line, Construction of Ferrocement Pump house Construction of OHSR at Nayattukundu Mattathur Grammapanchayat Chalakkudy PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 Pipe laying work ongoing Chalakudy AE 1
07 May 2024 Pipe laying work ongoing Chalakudy AE 1
03 May 2024 Pipe laying work progressing Chalakudy AE 1
29 Apr 2024 Pipe laying work progressing Chalakudy AE 1
24 Apr 2024 Pipe laying work progressing Chalakudy AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/03/2024
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 23 Feb 2024
TS Date 01 Mar 2024

Other details

Project Officers View