DEPOSIT-Thrissur Corporation water supply section: Pipe line extension to Nettissery Akshaya street one to Sky valley ,Nettiseery aal to Keechery bridge, Nettissery Sivapuram road, Nettissery Matrika Street, Nettissery Kalladi moola to Mahi transformer in Division No 16-in Thrissur corporation

Project DEPOSIT-Thrissur Corporation water supply section: Pipe line extension to Nettissery Akshaya street one to Sky valley ,Nettiseery aal to Keechery bridge, Nettissery Sivapuram road, Nettissery Matrika Street, Nettissery Kalladi moola to Mahi transformer in Division No 16-in Thrissur corporation
Project Code TCRDEPO112213407
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Thrissur Corporation water supply section: Pipe line extension to Nettissery Akshaya street one to Sky valley ,Nettiseery aal to Keechery bridge, Nettissery Sivapuram road, Nettissery Matrika Street, Nettissery Kalladi moola to Mahi transformer in Division No 16-in Thrissur corporation
Status Completed
District Thrissur
Executing Office Thrissur WW Sn 1
AS Amount (Rs) 2100000
AS Number WS1-19018/2018
TS Amount (Rs) 2100000
TS Number WRD/KWA-CE(CR)/EST_TS/15107/2022_5_1_1 Dated: 30-12-2022
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 21 Mar 2023
Coverage

Packages

No. Project Name Location View
1 DEPOSIT-Thrissur Corporation water supply section: Pipe line extension to Nettissery Akshaya street one to Sky valley ,Nettiseery aal to Keechery bridge, Nettissery Sivapuram road, Nettissery Matrika Street, Nettissery Kalladi moola to Mahi transformer in Division No 16-in Thrissur corporation Thrissur WW Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Aug 2023 Work completed on 21.03.2023. Bill paid ( UC fwd) Thrissur PH Dn EE
23 Mar 2023 work completed(21/03/2023) Thrissur WW Sn - AE 1
20 Mar 2023 Pipe laying work in progress Thrissur WW Sn - AE 1
16 Mar 2023 Pipe laying work in progress Thrissur WW Sn - AE 1
09 Mar 2023 Pipe laying work in progress Thrissur WW Sn - AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/01/2023
Scheduled date of Completion of the Project 16 Mar 2023
Expected date of Completion 16/03/2023

Processing Dates

AS Date 05 Nov 2022
TS Date 30 Dec 2022

Other details

Project Officers View