Project | State Plan 2023-24-UWSS to Kothamangalam Municipality- Supplying, erection and commissioning of one 25 HP CF pumpset and allied works in Vilayal PH in Kothamangalam Municipality. |
---|---|
Project Code | EKMGOK052314471P1 |
Type | Package |
Main Project | State Plan 2023-24-UWSS to Kothamangalam Municipality- Supplying, erection and commissioning of one 25 HP CF pumpset and allied works in Vilayal PH in Kothamangalam Municipality. |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | State Plan 2023-24-UWSS to Kothamangalam Municipality- Supplying, erection and commissioning of one 25 HP CF pumpset and allied works in Vilayal PH in Kothamangalam Municipality. |
Status | On-going |
District | Ernakulam |
Executing Office | Kothamangalam Sn 1 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 1060000 |
TS Number | TS/5398/2023_26_1_1 dated 01/11/2023 Reg No.17858/2023-2024 |
Technical specification | Supplying, erection and commissioning of one 25 HP CF pumpset and allied works in Vilayal PH in Kothamangalam Municipality. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/12/2023 |
---|---|
Scheduled date of Completion as per agreement | 20 Jun 2024 |
Expected date of Completion | Date is not specified |
TS Date | 01 Nov 2023 |
---|---|
Estimate Approval | 01 Nov 2023 |
NIT Approval | 01 Nov 2023 |
Tender Closing | 01 Dec 2023 |
Technichal Pre-Qualification | 01 Dec 2023 |
Price bid opening | 04 Dec 2023 |
Workorder Date | 18 Dec 2023 |
---|---|
NA | 21 Dec 2023 |
Kothamangalam PH Sn 1 - AE |
Date: 20/04/2024 |
Work in progress | 25% Completed
Induction motor reached at site.
Kothamangalam PH Sn 1 - AE |
Date: 15/03/2024 |
Work has started | 0% Completed
Agreement executed.