JJM Upputhara Grama panchayath - Coverage of Fluride affected habitation in ward 14 Kaithappathal&Karintharuvi and Providing Functional househould tap connnections FHTC to rural households
| Project |
JJM Upputhara Grama panchayath - Coverage of Fluride affected habitation in ward 14 Kaithappathal&Karintharuvi and Providing Functional househould tap connnections FHTC to rural households |
| Project Code |
IDKJJM12205935 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-92-01 |
| Description |
JJM Upputhara Grama panchayath - Coverage of Fluride affected habitation in ward 14 Kaithappathal&Karintharuvi and Providing Functional househould tap connnections FHTC to rural households
|
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Thodupuzha PH Dn |
| AS Amount (Rs) |
6820000
|
| AS Number |
G.O.(Rt)No.777/2020/WRD |
| TS Amount (Rs) |
6820000 |
| TS Number |
0.0 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
800 |
| Capacity in MLD |
2.00 |
| Actual Project Completion Date |
26 Sep 2023 |
| Coverage |
Upputhara |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Package 1:- JJM Upputhara Grama panchayath - Coverage of Fluride affected habitation in ward 14 Kaithappathal&Karintharuvi and Providing Functional househould tap connnections FHTC to rural households |
Peerumedu Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 20 Jan 2024 |
completed |
Peerumedu Sn AE |
|
| 19 Jan 2024 |
84 connections provided |
Peerumedu Sn AE |
|
| 14 Sep 2022 |
Work re tendered and due date 19.09.2022 |
Peerumedu AEE |
|
| 14 Sep 2022 |
Work re tendered. |
Peerumedu Sn AE |
|
| 13 Sep 2022 |
Work re tendered. |
Peerumedu Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
08/10/2022 |
| Scheduled date of Completion of the Project |
07 Apr 2023 |
| Expected date of Completion |
26/09/2023 |
Processing Dates
| AS Date |
24 Dec 2020 |
| TS Date |
20 Aug 2022 |