Deposit work - 2019-2020 - Providing pipe line extension and street tap at various wards in Thalikulam GP
Project |
Deposit work - 2019-2020 - Providing pipe line extension and street tap at various wards in Thalikulam GP |
Project Code |
TCRDEPO09208204 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work - 2019-2020 - Providing pipe line extension and street tap at various wards in Thalikulam GP |
Status |
Dropped |
District |
Thrissur |
Executing Office |
Vadanappalli Sn |
AS Amount (Rs) |
240000
|
AS Number |
A3-1729/20 |
TS Amount (Rs) |
240000 |
TS Number |
TS/2020-2021/2020/3377 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
1500 |
Capacity in MLD |
|
Actual Project Completion Date |
19 Jan 2022 |
Coverage |
street tap at various wards in Thalikulam GP |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work - 2019-2020 - Providing pipe line extension and street tap at various wards in Thalikulam GP |
Vadanappalli Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Nov 2022 |
project dropped |
Vadanappilly AE |
|
07 Nov 2022 |
Letter issued by AE to Thalikulam Panchayath President for confirming the Project excluding Street Tap erections are not entertained |
Vadanappilly AE |
|
03 Nov 2022 |
Letter issued by AE to Thalikulam Panchayath President for confirming the Project excluding Street Tap erections are not entertained |
Vadanappilly AE |
|
31 Oct 2022 |
Letter issued by AE to Thalikulam Panchayath President for confirming the Project excluding Street Tap erections are not entertained |
Vadanappilly AE |
|
27 Oct 2022 |
Letter issued by AE to Thalikulam Panchayath President for confirming the Project excluding Street Tap erections are not entertained |
Vadanappilly AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
19 Jan 2022 |
Expected date of Completion |
30/12/2022 |
Processing Dates
AS Date |
03 Sep 2020 |
TS Date |
30 Sep 2020 |