Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT SAAP -2016-17-WSS to Palakkad Municipality-Phase II-Package II-Construction of 45 MLD WTP at Malampuzha

Project AMRUT SAAP -2016-17-WSS to Palakkad Municipality-Phase II-Package II-Construction of 45 MLD WTP at Malampuzha
Project Code PKDAMRUT09173150
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Construction of 45 MLD water treatment plant at Malampuzha KWA compound
Status Completed
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 222500000
AS Number GO(Rt) No.3170/LSGD
TS Amount (Rs) 222500000
TS Number KWA/CE/NR/20/17-18
Total Bill Submitted (Rs) 157036402
Total Bill Paid (Rs) 142998257
Population Benefitted 172683
Capacity in MLD 45.00
Actual Project Completion Date 30 May 2022
Coverage Palakkad Municipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT 2016-17 Phase II-Package II Palakkad WSS- Construction of 45MLD WTP at Malampuzha Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 May 2022 All work completed Palakkad Proj AE 3
28 May 2022 Scada monitoring installation Completed, minor Finishing works in progress Palakkad Project Dn AE 4
27 May 2022 Scada monitoring installation Completed, minor Finishing works in progress Palakkad Project Dn AE 4
26 May 2022 Commissioning works,Scada monitoring installation works in progress Palakkad Project Dn AE 4
25 May 2022 Commissioning works,Scada monitoring installation works in progress Palakkad Project Dn AE 4

Project Review

See All Review messages
Review Date Review Message Review Attended By
07 Nov 2021 Need to speed up remaining works including pipe laying;mechanical finishing works and filter media filling .Ask contractor to ado electrification of building immediately. AE,AEE

Duration & Sanction dates

Date of start of Project 15/06/2020
Scheduled date of Completion of the Project 25 Jan 2021
Expected date of Completion 20/05/2022

Processing Dates

AS Date 28 Sep 2017
TS Date 08 Nov 2017

Other details

Project Officers View