Project | Deposit - Jilla Panchayath - ARWSS to Krishnagiri and Purakkadi villages - WSS to Paanchami colony of Ward No.XVII in Meenangadi GP |
---|---|
Project Code | WYDDEPO022314311P1 |
Type | Package |
Main Project | Deposit - Jilla Panchayath - ARWSS to Krishnagiri and Purakkadi villages - WSS to Paanchami colony of Ward No.XVII in Meenangadi GP |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit - Jilla Panchayath - ARWSS to Krishnagiri and Purakkadi villages - WSS to Paanchami colony of Ward No.XVII in Meenangadi GP |
Status | On-going |
District | Wayanad |
Executing Office | Sulthan Bathery Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 1240000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/3475/2023_26_1_1 |
Technical specification | WSS to Paanchami colony of Ward No.XVII in Meenangadi |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 13/06/2023 |
---|---|
Scheduled date of Completion as per agreement | 12 Dec 2023 |
Expected date of Completion | 30/06/2024 |
TS Date | 20 Apr 2023 |
---|---|
Estimate Approval | 20 Apr 2023 |
NIT Approval | 20 Apr 2023 |
Tender Closing | 16 May 2023 |
Technichal Pre-Qualification | 16 May 2023 |
Price bid opening | 17 May 2023 |
Workorder Date | 02 Jun 2023 |
---|---|
NA | 13 Jun 2023 |
Sulthan Bathery PH Dn EE |
Date: 13/05/2024 |
Work in progress | 96% Completed
pipe line work completed.
Sulthan Bathery PH Sn - AE |
Date: 04/05/2024 |
Work in progress | 96% Completed
pipe line work completed.