- Home
- Jal Jeevan Mission 2020-2021 - Retrofitt...
Jal Jeevan Mission 2020-2021 - Retrofitting and Providing FHTCs in Puthur Grama Panchayat in Thrissur District
Project |
Jal Jeevan Mission 2020-2021 - Retrofitting and Providing FHTCs in Puthur Grama Panchayat in Thrissur District |
Project Code |
TCRJJM08205235 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission 2020-2021 - Retrofitting and Providing FHTCs in Puthur Grama Panchayat in Thrissur District |
Status |
On-going |
District |
Thrissur |
Executing Office |
Peechi PH Sn |
AS Amount (Rs) |
24500000
|
AS Number |
GO (Rt) no 541/2020/WRD |
TS Amount (Rs) |
24500000 |
TS Number |
TS/2020-2021/2020/14333 |
Total Bill Submitted (Rs) |
1000000 |
Total Bill Paid (Rs) |
1000000 |
Population Benefitted |
15000 |
Capacity in MLD |
36.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Puthur Grama Panchayat |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission 2019-2020- Providing FHTCs to Puthur GP-supply,erection,testing and commissioning of KWA prequalified reputed make open well submersible pump set with discharge 17 lps against 100m head |
Peechi PH Sn |
|
2 |
Jal Jeevan Mission 2020-2021 - Retrofitting and Providing FHTCs in Puthur Gram Panchayath in Thrissur District |
Peechi PH Sn |
|
3 |
JJM Support activities- RWSS to Vettukkad and RWSS Marathakkara automation of borewell pump houses under PH section peechi |
Peechi PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 May 2024 |
819 FHTCs and 181 HTCs Given. |
Thrissur PH Dn EE |
|
14 May 2024 |
819 FHTCs and 181 HTCs Given. |
Thrissur PH Dn EE |
|
13 May 2024 |
819 FHTCs and 181 HTCs Given. |
Thrissur PH Dn EE |
|
10 May 2024 |
819 FHTCs and 181 HTCs Given. |
Thrissur PH Dn EE |
|
09 May 2024 |
819 FHTCs and 181 HTCs Given. |
Thrissur PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/06/2021 |
Scheduled date of Completion of the Project |
30 Jun 2022 |
Expected date of Completion |
31/05/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
05 Sep 2020 |