AMRUT 2 - Palakkad Municipality Providing new House Connections and carrying out works in Pipelines and to improve water supply levels in the connections
Project |
AMRUT 2 - Palakkad Municipality Providing new House Connections and carrying out works in Pipelines and to improve water supply levels in the connections |
Project Code |
PKDAMRUT122214325 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT 2 - Palakkad Municipality Providing new House Connections and carrying out works in Pipelines and to improve water supply levels in the connections |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Revenue Sn |
AS Amount (Rs) |
188000000
|
AS Number |
KWA/JB/PIU2/10/JJM-URBAN/2021PART III |
TS Amount (Rs) |
33300000 |
TS Number |
.0 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1500 |
Capacity in MLD |
45.00 |
Actual Project Completion Date |
28 Feb 2024 |
Coverage |
SEKHAREEPURAM,VADAKKANTHARA, KUNNATHURMEDU, PUTHUR, AND VARIOUS PLACES IN PALAKKAD MUNICIPALITY |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-AMRUT 2.0-Palakkad MuncipalityProviding new House Connections and carrying out works in Pipelines to improve water supply levels in the connections-Kunnathurmedu and Stadium Court Road-Part 2-Pipeline Work |
Palakkad Revenue Sn |
|
2 |
AMRUT-AMRUT 2.0-Palakkad Muncipality-Providing new House Connections and carrying out works in Pipelines to improve water supply levels in the connections-Sai Hospital to Nadakavu gate-Part 4-Pipeline Work |
Palakkad Revenue Sn |
|
3 |
AMRUT-AMRUT 2.0-Palakkad MuncipalityProviding new House Connections and carrying out works in Pipelines to improve water supply levels in the connections-Sekharipuram-Part 1- Pipeline Work |
Palakkad Revenue Sn |
|
4 |
AMRUT-AMRUT 2.0-Palakkad Muncipality-Providing new House Connections and carrying out works in Pipelines to improve water supply levels in the connections-Vadakkanthara road.-Part 3-Pipeline Work |
Palakkad Revenue Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Jun 2023 |
Tendered 5 times from SE PHC, PKD, Nobody quoted. Hence directed to recast the estimate into 19 packages. 4 estimate TS had been issued by EE on 8.6.23 and tendered
Balance TS to be issued by EE by 30/6/23 & to be tendered by 10/7/23. Out of 4 works tendered in which 2 works has no offers, so extended upto 20/06/2023. |
Palakkad PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/10/2023 |
Scheduled date of Completion of the Project |
28 Feb 2024 |
Expected date of Completion |
28/02/2024 |
Processing Dates
AS Date |
01 Dec 2022 |
TS Date |
08 Jun 2023 |