Augumentation of WSS to N Paravur Municipality and adjoining Pts. - Supply, Erection, Testing &commissioning of 1 Nos. best Quality reputed make centrifugal pump set having a discharge of 78.5lps against a total head of 55 m at N Paravur Pump House. Water supply for Chendamangalam pt and N Paravur Muncipality

Project Augumentation of WSS to N Paravur Municipality and adjoining Pts. - Supply, Erection, Testing &commissioning of 1 Nos. best Quality reputed make centrifugal pump set having a discharge of 78.5lps against a total head of 55 m at N Paravur Pump House. Water supply for Chendamangalam pt and N Paravur Muncipality
Project Code EKMGOK08184057P1
Type Package
Main Project Augumentation of WSS to N Paravur Municipality and adjoining Pts. - Supply, Erection, Testing &commissioning of 1 Nos. best Quality reputed make centrifugal pump set having a discharge of 78.5lps against a total head of 55 m at N Paravur Pump House. Water supply for Chendamangalam pt and N Paravur Muncipality
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Augumentation of WSS to N Paravur Municipality and adjoining Pts. - Supply, Erection, Testing &commissioning of 1 Nos. best Quality reputed make centrifugal pump set having a discharge of 78.5lps against a total head of 55 m at N Paravur Pump House. Water supply for Chendamangalam pt and N Paravur Muncipality
Status Completed
District Ernakulam
Executing Office Kochi WS Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/07/2019
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 26/08/2019

Processing Dates

AS Date 20 Aug 2018
TS Date 30 Nov 2018
Tender Closing 24 Dec 2018

Approval Dates

Workorder Date 18 Feb 2019
NA 08 Mar 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kochi WS Dn EE
Date: 23/11/2020

Work has been completed | 100% Completed

Work completed bill submitted .