DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara
Project |
DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara |
Project Code |
IDKGOK112213313 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
DEPOSIT-KRFB-Hill Highway KRFB-2017-2018-Improvements to Peerumedu, Devikulam Road KM 19/000 to 40/050 and Thodupuzha - Puliyanmala road KM 85/500 to 92/167 in Idukki dist Marykulam-Nariyampara - Shifting of KWA utilities Pipeline work |
Status |
On-going |
District |
Idukki |
Executing Office |
Kattappana Project Dn |
AS Amount (Rs) |
50359930
|
AS Number |
KRFB-PMU/MVPA-IDK/HH-PD/2021 |
TS Amount (Rs) |
27860000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/12798/2022_26_1_1 |
Total Bill Submitted (Rs) |
12318894 |
Total Bill Paid (Rs) |
12318894 |
Population Benefitted |
56780 |
Capacity in MLD |
7.00 |
Actual Project Completion Date |
06 May 2023 |
Coverage |
Marykulam-Nariyampara |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara |
Project Division Kattapana |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
Pipeline works are ongoing. So far laid 3598.5 meters of 90mm PVC pipe, 2710 meters of 160 mm PVC pipe, 577 meters of 250mm DI, 2041 meters of 200mm PVC pipe, 227 meters of 80mm GI pipe and 186.39 meters of 150mm GI pipe. |
Kattappana AEE 1 |
|
10 May 2024 |
Pipeline works are ongoing. So far laid 3598.5 meters of 90mm PVC pipe, 2710 meters of 160 mm PVC pipe, 577 meters of 250mm DI, 2041 meters of 200mm PVC pipe, 227 meters of 80mm GI pipe and 186.39 meters of 150mm GI pipe. |
Kattappana AEE 1 |
|
07 May 2024 |
Pipeline works are ongoing. So far laid 3598.5 meters of 90mm PVC pipe, 2710 meters of 160 mm PVC pipe, 577 meters of 250mm DI, 2023 meters of 200mm PVC pipe, 227 meters of 80mm GI pipe and 186.39 meters of 150mm GI pipe. |
Kattappana AEE 1 |
|
04 May 2024 |
Pipeline works are ongoing. So far laid 3598.5 meters of 90mm PVC pipe, 2620 meters of 160 mm PVC pipe, 577 meters of 250mm DI, 1768 meters of 200mm PVC pipe, 227 meters of 80mm GI pipe and 162.04 meters of 150mm GI pipe. |
Kattappana AEE 1 |
|
01 May 2024 |
Pipeline works are ongoing. So far laid 3598.5 meters of 90mm PVC pipe, 2620 meters of 160 mm PVC pipe, 577 meters of 250mm DI, 1645 meters of 200mm PVC pipe, 227 meters of 80mm GI pipe and 162.04 meters of 150mm GI pipe. |
Kattappana AEE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/01/2023 |
Scheduled date of Completion of the Project |
14 Apr 2023 |
Expected date of Completion |
14/04/2023 |
Processing Dates
AS Date |
01 Nov 2022 |
TS Date |
09 Dec 2022 |