AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS IN KOLLAM CORPORATION

Project AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS IN KOLLAM CORPORATION
Project Code KLMAMRUT112213823
Type Main project
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNICIPAL AREA IN KOLLAM CORPORATION
Status On-going
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 220000000
AS Number G.O.(Rt)No.2906/2022/LSGD
TS Amount (Rs) 200000000
TS Number WRD/KWA-CE(SR)/EST_TS/1091/2022_26_1_1 Dated: 19-01-2023
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 40350
Capacity in MLD 11.00
Actual Project Completion Date Date is not specified
Coverage 55 Divisions in Kollam corporation
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREA UNDER KOLLAM CORPORATION-AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREAS UNDER KOLLAM CORPORATION Kollam WS Sn 2
2 AMRUT- 2.0 - RETROFIT AND PROVIDING NEW WATER CONNECTION AT VADAKKEVILA, ERAVIPURAM & KILIKOLLOOR AREA UNDER KOLLAM CORPORATION Kollam WS Sn 3
3 AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNCIPAL AREA IN KOLLAM CORPORATION Kollam WS Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 Package-I-26 % completed, 185 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-48 % completed , 1449 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-64 % completed , 698 nos FHTCs are given, Total Pipe laid till date- 12150 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
08 May 2024 Package-I-26 % completed, 178 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-47 % completed , 1350 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-63 % completed , 670 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
04 May 2024 Package-I-26 % completed, 165 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-46 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-63 % completed , 629 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
30 Apr 2024 Package-I-26 % completed, 165 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-45 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-62 % completed , 588 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
27 Apr 2024 Package-I-25 % completed, 162 nos FHTCs are given,Total Pipe laid till date-3410m (FHTCS and pipe laying in progress . Package-II-45 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-61 % completed , 542 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/05/2023
Scheduled date of Completion of the Project 08 May 2024
Expected date of Completion 01/05/2024

Processing Dates

AS Date 24 Nov 2022
TS Date 19 Jan 2023