- Home
- AMRUT-2.0-RETROFITTING AND PROVIDING NEW...
AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS IN KOLLAM CORPORATION
Project |
AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS IN KOLLAM CORPORATION |
Project Code |
KLMAMRUT112213823 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNICIPAL AREA IN KOLLAM CORPORATION |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam PH Dn |
AS Amount (Rs) |
220000000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
200000000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/1091/2022_26_1_1 Dated: 19-01-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
40350 |
Capacity in MLD |
11.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
55 Divisions in Kollam corporation |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREA UNDER KOLLAM CORPORATION-AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREAS UNDER KOLLAM CORPORATION |
Kollam WS Sn 2 |
|
2 |
AMRUT- 2.0 - RETROFIT AND PROVIDING NEW WATER CONNECTION AT VADAKKEVILA, ERAVIPURAM & KILIKOLLOOR AREA UNDER KOLLAM CORPORATION |
Kollam WS Sn 3 |
|
3 |
AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNCIPAL AREA IN KOLLAM CORPORATION |
Kollam WS Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
Package-I-26 % completed, 185 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-48 % completed , 1449 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-64 % completed , 698 nos FHTCs are given, Total Pipe laid till date- 12150 m -Restoration of road by laying concrete concrete under progress. |
Kollam WS Sn 2 - AE |
|
08 May 2024 |
Package-I-26 % completed, 178 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-47 % completed , 1350 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-63 % completed , 670 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. |
Kollam WS Sn 2 - AE |
|
04 May 2024 |
Package-I-26 % completed, 165 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-46 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-63 % completed , 629 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. |
Kollam WS Sn 2 - AE |
|
30 Apr 2024 |
Package-I-26 % completed, 165 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-45 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-62 % completed , 588 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. |
Kollam WS Sn 2 - AE |
|
27 Apr 2024 |
Package-I-25 % completed, 162 nos FHTCs are given,Total Pipe laid till date-3410m (FHTCS and pipe laying in progress . Package-II-45 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-61 % completed , 542 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. |
Kollam WS Sn 2 - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
17/05/2023 |
Scheduled date of Completion of the Project |
08 May 2024 |
Expected date of Completion |
01/05/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
19 Jan 2023 |