Deposit work of Tvpm Corporation- Project No-S0548/22-Altration of existing connections in the old AC pipe to the new 110mm PVC JNNURM line at Sivaji Nagar at Attipra ward
Project |
Deposit work of Tvpm Corporation- Project No-S0548/22-Altration of existing connections in the old AC pipe to the new 110mm PVC JNNURM line at Sivaji Nagar at Attipra ward |
Project Code |
TVMDEPO032211551 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work of Tvpm Corporation- Project No-S0548/22-Altration of existing connections in the old AC pipe to the new 110mm PVC JNNURM line at Sivaji Nagar at Attipra ward |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kazhakootam WW Sn |
AS Amount (Rs) |
573000
|
AS Number |
J4/548/21 |
TS Amount (Rs) |
571000 |
TS Number |
349/2022-23 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
200 |
Capacity in MLD |
0.05 |
Actual Project Completion Date |
24 Sep 2022 |
Coverage |
Alteration from the existing 80 mm AC to the JNNURM PVC 110 mm
100 - Nos. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Tvpm Corporation- Project No-S0548/22-Altration of existing connections in the old AC pipe to the new 110mm PVC JNNURM line at Sivaji Nagar at Attipra ward |
Kazhakootam WW Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Nov 2022 |
Completed |
Kazhakootam WW Sn AE |
|
10 Nov 2022 |
Work Ongoing |
Kazhakootam WW Sn AE |
|
07 Nov 2022 |
Work Ongoing |
Kazhakootam WW Sn AE |
|
03 Nov 2022 |
Work Ongoing |
Kazhakootam WW Sn AE |
|
31 Oct 2022 |
Work Ongoing |
Kazhakootam WW Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/08/2022 |
Scheduled date of Completion of the Project |
24 Sep 2022 |
Expected date of Completion |
24/09/2022 |
Processing Dates
AS Date |
24 Mar 2022 |
TS Date |
07 Apr 2022 |