Project | AMRUT-AMRUT 2.0 - AUGMENTATION OF WSS TO MAVELIKKARA MUNICIPALITY- Replacing old and damaged AC pipelines |
---|---|
Project Code | ALPAMRUT032313794P2 |
Type | Package |
Main Project | Amrut 2.0-UWSS to Mavelikkara Municipality |
Funding Agency | AMRUT 2 |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | |
Description | AMRUT-AMRUT 2.0 - AUGMENTATION OF WSS TO MAVELIKKARA MUNICIPALITY- Replacing old and damaged AC pipelines-supplying and laying distribution- 110 mm PVC (8kg/cm2)-14000m 160 mm PVC (8kg/cm2)-1000m |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 69800000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/5011/2022_5_1_1 |
Technical specification | supplying and laying distribution- 110 mm PVC (8kg/cm2)-14000m 160 mm PVC (8kg/cm2)-1000m |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 22 May 2023 |
---|---|
Estimate Approval | 22 May 2023 |
Alappuzha Project Dn PM |
Date: 20/05/2024 |
Work in progress | 62% Completed
110 mm PVC laid out of 13000 meter PVC pipe to be laid 10117 meter laying has been completed, 160 mm PVC laid out of 2000 meter PVC pipe to be laid 0 m meter laying has been completed. .
Alappuzha Project Dn PM |
Date: 19/05/2024 |
Work in progress | 62% Completed
110 mm PVC laid out of 13000 meter PVC pipe to be laid 10117 meter laying has been completed, 160 mm PVC laid out of 2000 meter PVC pipe to be laid 0 m meter laying has been completed. .