- Home
- State Plan 2019 - 2020 TSS - Tertiary Tr...
State Plan 2019 - 2020 TSS - Tertiary Treatment of Sewage at STP Muttathara.
Project |
State Plan 2019 - 2020 TSS - Tertiary Treatment of Sewage at STP Muttathara. |
Project Code |
TVMGOK06191797 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Construction of 5MLD Treatment Plant at STP Muttathara.
G.O.(Rt)No. 419/2019/WRD dated 14.06.2019 |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Plamoodu project Sn |
AS Amount (Rs) |
50000000
|
AS Number |
419/2019/WRD |
TS Amount (Rs) |
48200000 |
TS Number |
10254/2020-2021 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
500000 |
Capacity in MLD |
5.00 |
Actual Project Completion Date |
01 Apr 2023 |
Coverage |
Construction of 5MLD Treatment Plant at STP Muttathara.
G.O.(Rt)No. 419/2019/WRD dated 14.06.2019 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan 2019 - 2020 TSS - Tertiary Treatment of Sewage at STP Muttathara. |
Plamoodu project Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
Firm has been directed to execute the subject work according to the NIT condition of the work and to complete within the approved schedule |
Plamoodu Sewerage Project Sn AE |
|
10 May 2024 |
Firm has been directed to execute the subject work according to the NIT condition of the work and to complete within the approved schedule |
Plamoodu Sewerage Project Sn AE |
|
08 May 2024 |
Firm has been directed to execute the subject work according to the NIT condition of the work and to complete within the approved schedule |
Plamoodu Sewerage Project Sn AE |
|
06 May 2024 |
Firm has been directed to execute the subject work according to the NIT condition of the work and to complete within the approved schedule |
Plamoodu Sewerage Project Sn AE |
|
04 May 2024 |
Firm has been directed to execute the subject work according to the NIT condition of the work and to complete within the approved schedule |
Plamoodu Sewerage Project Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/04/2022 |
Scheduled date of Completion of the Project |
01 Apr 2023 |
Expected date of Completion |
31/10/2023 |
Processing Dates
AS Date |
14 Jun 2019 |
TS Date |