State Plan 2020-21 - "Source improvement of Sasthamcotta water treatment plant" - Construction of recycling plant at Sasthamcotta in Kollam District.

Project State Plan 2020-21 - "Source improvement of Sasthamcotta water treatment plant" - Construction of recycling plant at Sasthamcotta in Kollam District.
Project Code KLMGOK04206064
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description The work is proposed to construct the recycling plant at water treatment plant Sasthamcotta. It includes roughing filter,wash water collection tank,sludge lagoon etc
Status On-going
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 30200000
AS Number KWA/JB/HO/Sn(O)/1/75/2016 .22598/AE 1/2022/KWA
TS Amount (Rs) 26172000
TS Number 16886/2020-2021
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 50000
Capacity in MLD 37.50
Actual Project Completion Date Date is not specified
Coverage Retendered the work tender opening date is on 26/08/2021
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2020-21 - "Source improvement of Sasthamcotta water treatment plant" - Construction of recycling plant at Sasthamcotta in Kollam District. Sasthamcottah WS Sn2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 Tender invited at circle office several times ,no offer received and directed to recast the estimate . AS also obtained vide AS No.: 22598/AE 1/2022/KWA dated 15.05.2023 for an amount of 40.28 lakhs for the balance work hence combined estimate is prepared which is scrutiny under division Sasthamcotta WS Sn 2 HW - AE
09 May 2024 Tender invited at circle office several times ,no offer received and directed to recast the estimate . AS also obtained vide AS No.: 22598/AE 1/2022/KWA dated 15.05.2023 for an amount of 40.28 lakhs for the balance work hence combined estimate is prepared which is scrutiny under division Sasthamcotta WS Sn 2 HW - AE
06 May 2024 Tender invited at circle office several times ,no offer received and directed to recast the estimate . AS also obtained vide AS No.: 22598/AE 1/2022/KWA dated 15.05.2023 for an amount of 40.28 lakhs for the balance work hence combined estimate is prepared which is scrutiny under division Sasthamcotta WS Sn 2 HW - AE
03 May 2024 Tender invited at circle office several times ,no offer received and directed to recast the estimate . AS also obtained vide AS No.: 22598/AE 1/2022/KWA dated 15.05.2023 for an amount of 40.28 lakhs for the balance work hence combined estimate is prepared which is scrutiny under division Sasthamcotta WS Sn 2 HW - AE
29 Apr 2024 Tender invited at circle office several times ,no offer received and directed to recast the estimate . AS also obtained vide AS No.: 22598/AE 1/2022/KWA dated 15.05.2023 for an amount of 40.28 lakhs for the balance work hence combined estimate is prepared which is scrutiny under division Sasthamcotta WS Sn 2 HW - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/11/2021
Scheduled date of Completion of the Project 22 May 2022
Expected date of Completion 30/06/2022

Processing Dates

AS Date 15 May 2023
TS Date 12 Feb 2021

Other details