JJM-2020-21-Phase I-Balance work -Kallara Panchayath - Providing FHTC in various wards by Retrofitting /Augmenting /Extending the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy

Project JJM-2020-21-Phase I-Balance work -Kallara Panchayath - Providing FHTC in various wards by Retrofitting /Augmenting /Extending the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Project Code KTMJJM08204317P2
Type Package
Main Project JJM-2020-21-Kallara Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM-2020-21-Phase I-Balance work -Kallara Panchayath - Providing FHTC in various wards by Retrofitting /Augmenting /Extending the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Status On-going
District Kottayam
Executing Office Kaduthuruthy Sn
Agreement Number
Agreement Date
TS Amount (Rs) 7300000
TS Number ORDER No. TS/2021-2022/2021/43110Dated: 11-01-2022
Technical specification JJM-2020-21-Phase I-Balance work -Kallara Panchayath - Providing FHTC in various wards by Retrofitting /Augmenting /Extending the existing distribution system should covered with a population of 12500
Contractor ALIAS K KURIYAKOSE (Mob: 9447294254)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 11/03/2022
Scheduled date of Completion as per agreement 24 Jun 2022
Expected date of Completion 24/06/2022

Processing Dates

TS Date 11 Jan 2022
Estimate Approval 24 Jan 2022
NIT Approval 24 Jan 2022
Tender Closing 01 Feb 2022
Technichal Pre-Qualification 23 Jan 2022
Price bid opening 04 Feb 2022

Approval Dates

Workorder Date 11 Feb 2022
NA 25 Feb 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kaduthuruthy Dn EE
Date: 30/08/2022

Work has been completed | 100% Completed

work completed bill submitted .

Kaduthuruthy Dn EE
Date: 29/08/2022

Work in progress | 98% Completed

work completed bill under preparation .