DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH

Project DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH
Project Code ALPDEPO032313988
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH
Status Completed
District Alappuzha
Executing Office Harippad PH Sn
AS Amount (Rs) 79000
AS Number H L-2450(7)/22
TS Amount (Rs) 79000
TS Number ORDER No.: WRD/KWA-CE(CR)/EST_TS/1969/2023_26_1_1 Dated: 11-04-2023
Total Bill Submitted (Rs) 41404
Total Bill Paid (Rs) 40000
Population Benefitted 1000
Capacity in MLD 0.10
Actual Project Completion Date 08 Jun 2023
Coverage DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH

Packages

No. Project Name Location View
1 DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH Harippad PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Jun 2023 Work completed, Bill Submitted. Harippad PH Sn - AE
05 Jun 2023 Work Completed Harippad PH Sn - AE
29 May 2023 Work Completed Harippad PH Sn - AE
25 May 2023 Work in progress Harippad PH Sn - AE
22 May 2023 Work in progress Harippad PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/04/2023
Scheduled date of Completion of the Project 11 May 2023
Expected date of Completion 11/05/2023

Processing Dates

AS Date 21 Mar 2023
TS Date 11 Apr 2023

Other details

Project Officers View