DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH
Project |
DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH |
Project Code |
ALPDEPO032313988 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Harippad PH Sn |
AS Amount (Rs) |
79000
|
AS Number |
H L-2450(7)/22 |
TS Amount (Rs) |
79000 |
TS Number |
ORDER No.: WRD/KWA-CE(CR)/EST_TS/1969/2023_26_1_1 Dated: 11-04-2023 |
Total Bill Submitted (Rs) |
41404 |
Total Bill Paid (Rs) |
40000 |
Population Benefitted |
1000 |
Capacity in MLD |
0.10 |
Actual Project Completion Date |
08 Jun 2023 |
Coverage |
DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT- DEPOSIT WORK - 2022-23:- KARTHIKAPPLLY GRAMA PANCHAYAT.- INTERCONNECTION WORK BETWEEN MALIYECKAL (BIPIN LAL BHAVANAM) TO VAISAK BHAVANAM (S.N NAGAR- KOCHAR ROAD) IN WARD 13 OF KARTHIKAPPALLY GRAMA PANCHAYATH |
Harippad PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Jun 2023 |
Work completed, Bill Submitted. |
Harippad PH Sn - AE |
|
05 Jun 2023 |
Work Completed |
Harippad PH Sn - AE |
|
29 May 2023 |
Work Completed |
Harippad PH Sn - AE |
|
25 May 2023 |
Work in progress |
Harippad PH Sn - AE |
|
22 May 2023 |
Work in progress |
Harippad PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
27/04/2023 |
Scheduled date of Completion of the Project |
11 May 2023 |
Expected date of Completion |
11/05/2023 |
Processing Dates
AS Date |
21 Mar 2023 |
TS Date |
11 Apr 2023 |