- Home
- Deposit Work 2021-22 -RWSS to Meloor - D...
Deposit Work 2021-22 -RWSS to Meloor - Disconnection of Street Tap in various wards of Meloor Panchayath
Project |
Deposit Work 2021-22 -RWSS to Meloor - Disconnection of Street Tap in various wards of Meloor Panchayath |
Project Code |
TCRDEPO102213328 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Disconnection of Street Tap in various wards of Meloor Panchayath |
Status |
Completed |
District |
Thrissur |
Executing Office |
Chalakkudy PH Sn II |
AS Amount (Rs) |
500000
|
AS Number |
SC2-2838/2022 |
TS Amount (Rs) |
500000 |
TS Number |
TS/10029/2022_5-1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
6.00 |
Actual Project Completion Date |
20 Mar 2023 |
Coverage |
100% |
Packages
No. |
Project Name |
Location |
View |
1 |
Disconnection of Street Tap in various wards of Meloor Panchayath |
Chalakkudy PH Sn II |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Mar 2023 |
work completed |
Chalakudy AE 2 |
|
18 Mar 2023 |
work in progress |
Chalakudy AE 2 |
|
16 Mar 2023 |
work in progress |
Chalakudy AE 2 |
|
13 Mar 2023 |
work in progress |
Chalakudy AE 2 |
|
09 Mar 2023 |
work in progress |
Chalakudy AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
10 Oct 2022 |
TS Date |
21 Oct 2022 |