- 29-ARWSS toAmbalavayal-Relaying damaged...
29-ARWSS toAmbalavayal-Relaying damaged Pumping Main at Raw Water pumping station Kottor and relaying damaged distribution system from Manhappara to Nellarachal
Project |
29-ARWSS toAmbalavayal-Relaying damaged Pumping Main at Raw Water pumping station Kottor and relaying damaged distribution system from Manhappara to Nellarachal |
Project Code |
WYDGOK03163937 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State plan 15-16-29-ARWSS toAmbalavayal-Relaying damaged Pumping Main at Raw Water pumping station Kottor and relaying damaged distribution system from Manhappara to Nellarachal |
Status |
Completed |
District |
Wayanad |
Executing Office |
Sulthan Bathery PH Dn |
AS Amount (Rs) |
2500000
|
AS Number |
KWA/DB1/5560 |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
1606573 |
Total Bill Paid (Rs) |
1606573 |
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
21 Dec 2018 |
Coverage |
Ambalavayal pts |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
29-ARWSS toAmbalavayal-Relaying damaged Pumping Main at Raw Water pumping station Kottor and relaying damaged distribution system from Manhappara to Nellarachal |
Sulthan Bathery Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Oct 2021 |
Work Completed |
Sulthan Bathery PH Dn EE |
|
23 Sep 2021 |
Work Completed |
Sulthan Bathery PH Dn EE |
|
16 Oct 2020 |
work completed |
Sulthan Bathery PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/02/2018 |
Scheduled date of Completion of the Project |
31 Oct 2018 |
Expected date of Completion |
21/12/2018 |
Processing Dates
AS Date |
29 Mar 2016 |
TS Date |
10 Oct 2017 |