| Project | ARWSS to Padinharathra and Thariode Villages - Inter connection works to Panthipoyil Transformer Junction to Bappanamala road junction |
|---|---|
| Project Code | WYDGOK03229646P3 |
| Type | Package |
| Main Project | DRW 2022 - Urgent Interconnection works |
| Funding Agency | GOK |
| Category | DRW |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | ARWSS to Padinharathra and Thariode Villages - Inter connection works to Panthipoyil Transformer Junction to Bappanamala road junction |
| Status | On-going |
| District | Wayanad |
| Executing Office | Sulthan Bathery Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 600000 |
| TS Number | TS/2022-2023/2022/13926 |
| Technical specification | interconnection works |
| Contractor | Abdulla K P (Mob: 9847372881) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 05/05/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 12 Sep 2022 |
| Expected date of Completion | 31/08/2022 |
| TS Date | 30 Apr 2022 |
|---|---|
| Estimate Approval | 30 Apr 2022 |
| NIT Approval | 12 May 2022 |
| Tender Closing | 19 May 2022 |
| Technichal Pre-Qualification | 23 May 2022 |
| Price bid opening | 10 Jan 2022 |
| Workorder Date | 23 May 2022 |
|---|---|
| NA | 13 Jun 2022 |
| Sulthan Bathery PH Dn EE |
| Date: 21/10/2023 |
Work has been completed | 100% Completed
Work has been completed.
| Sulthan Bathery PH Dn EE |
| Date: 05/10/2023 |
Work has been completed | 100% Completed
Work has been completed.