DEPOSIT- KDP -Ranni Block Panchayath 2022-23-WSS to Makkappuzha-[Project No-172/23]-Extension of pipe line in -Makkapuzha- Panavelikkuzhi road in Pazhavangadi Grama Panchayathu-Pipeline Work

Project DEPOSIT- KDP -Ranni Block Panchayath 2022-23-WSS to Makkappuzha-[Project No-172/23]-Extension of pipe line in -Makkapuzha- Panavelikkuzhi road in Pazhavangadi Grama Panchayathu-Pipeline Work
Project Code PTADEPO052314531
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT- KDP -Ranni Block Panchayath 2022-23-WSS to Makkappuzha-[Project No-172/23]-Extension of pipe line in -Makkapuzha- Panavelikkuzhi road in Pazhavangadi Grama Panchayathu-Pipeline Work
Status On-going
District Pathanamthitta
Executing Office Ranni Sub Dn
AS Amount (Rs) 472648
AS Number No.DBI-Price·2022/2023(EST/2395/2023(DEPO)
TS Amount (Rs) 472644
TS Number TS/2395/2023_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage DEPOSIT- KDP -Ranni Block Panchayath 2022-23-WSS to Makkappuzha-[Project No-172/23]-Extension of pipe line in -Makkapuzha- Panavelikkuzhi road in Pazhavangadi Grama Panchayathu-Pipeline Work

Packages

No. Project Name Location View
1 DEPOSIT- KDP -Ranni Block Panchayath 2022-23-WSS to Makkappuzha-[Project No-172/23]-Extension of pipe line in -Makkapuzha- Panavelikkuzhi road in Pazhavangadi Grama Panchayathu-Pipeline Work Ranni Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Feb 2024 Agreement Executed on 19/07/2023 Ranni PH Sn - AE
03 Jan 2024 Agreement Executed on 19/07/2023 Ranni PH Sn - AE
01 Jan 2024 Agreement Executed on 19/07/2023 Ranni PH Sn - AE
30 Dec 2023 Agreement Executed on 19/07/2023 Ranni PH Sn - AE
29 Dec 2023 Agreement Executed on 19/07/2023 Ranni PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/07/2023
Scheduled date of Completion of the Project 19 Oct 2023
Expected date of Completion 19/10/2023

Processing Dates

AS Date 29 May 2023
TS Date 29 May 2023

Other details