Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part I-Pipeline work

Project AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part I-Pipeline work
Project Code KNRAMRUT122315865P1
Type Package
Main Project AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part I-Pipeline work
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part I-Pipeline work
Status On-going
District Kannur
Executing Office Kannur WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 39000000
TS Number 23562/2023-24
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/02/2024
Scheduled date of Completion as per agreement 16 Apr 2024
Expected date of Completion 16/04/2024

Processing Dates

TS Date 06 Jan 2024
NIT Approval 08 Jan 2024
Tender Closing 15 Jan 2024
Price bid opening 16 Jan 2024

Approval Dates

Workorder Date 13 Feb 2024
NA 16 Feb 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kannur WS Sn AE 2
Date: 03/07/2025

Work in progress | 80% Completed

Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted.

Kannur WS Sn AE 2
Date: 30/06/2025

Work in progress | 80% Completed

Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted.