Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part I-Pipeline work |
---|---|
Project Code | KNRAMRUT122315865P1 |
Type | Package |
Main Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part I-Pipeline work |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Kannur Zone-Balance work-Kannur 2&3 Part I-Pipeline work |
Status | On-going |
District | Kannur |
Executing Office | Kannur WS Sn 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 39000000 |
TS Number | 23562/2023-24 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 26/02/2024 |
---|---|
Scheduled date of Completion as per agreement | 16 Apr 2024 |
Expected date of Completion | 16/04/2024 |
TS Date | 06 Jan 2024 |
---|---|
NIT Approval | 08 Jan 2024 |
Tender Closing | 15 Jan 2024 |
Price bid opening | 16 Jan 2024 |
Workorder Date | 13 Feb 2024 |
---|---|
NA | 16 Feb 2024 |
Kannur WS Sn AE 2 |
Date: 03/07/2025 |
Work in progress | 80% Completed
Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted.
Kannur WS Sn AE 2 |
Date: 30/06/2025 |
Work in progress | 80% Completed
Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted.