- Providing and laying 150mm SW sewer line...
Providing and laying 150mm SW sewer line for Public Comfort station near Kedaram shoppingcomplex at Kesavadasapuram under sewerage section Sasthamangalam-Sewerage Work
Project |
Providing and laying 150mm SW sewer line for Public Comfort station near Kedaram shoppingcomplex at Kesavadasapuram under sewerage section Sasthamangalam-Sewerage Work |
Project Code |
TVMGOK112213250 |
Type |
Main project |
Funding Agency |
GOK |
Category |
MLA ADS |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Providing and laying 150mm SW sewer line for Public Comfort station near Kedaram shoppingcomplex at Kesavadasapuram under sewerage section Sasthamangalam-Sewerage Work |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Sasthamangalam Sewerage Sn |
AS Amount (Rs) |
1901000
|
AS Number |
D1-3389/2022 |
TS Amount (Rs) |
1901000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/4424/2022_27_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
150 |
Capacity in MLD |
0.50 |
Actual Project Completion Date |
13 Feb 2023 |
Coverage |
Kesavadasapuram |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Providing and laying 150mm SW sewer line for Public Comfort station near Kedaram shoppingcomplex at Kesavadasapuram under sewerage section Sasthamangalam-Sewerage Work |
Sasthamangalam Sewerage Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Feb 2023 |
Work completed |
Sasthamangalam Sewerage Sn AE |
|
09 Feb 2023 |
Footpath tiling Pending |
Sasthamangalam Sewerage Sn AE |
|
06 Feb 2023 |
Footpath tiling Pending |
Sasthamangalam Sewerage Sn AE |
|
01 Feb 2023 |
Footpath tiling Pending |
Sasthamangalam Sewerage Sn AE |
|
28 Jan 2023 |
Footpath tiling Pending |
Sasthamangalam Sewerage Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
07/12/2022 |
Scheduled date of Completion of the Project |
06 Mar 2023 |
Expected date of Completion |
06/04/2023 |
Processing Dates
AS Date |
03 Nov 2022 |
TS Date |
21 Nov 2022 |