KIIFB Project 6 - RWSS to Thuneri Village- Replacing existing 200mm AC gravity main with 250mm DI K9 pipe from Nadapuram junction to Kakkamvellikkunnu GLSR

Project KIIFB Project 6 - RWSS to Thuneri Village- Replacing existing 200mm AC gravity main with 250mm DI K9 pipe from Nadapuram junction to Kakkamvellikkunnu GLSR
Project Code CLTKIIFB03191955
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description RWSS to Thuneri Village- Replacing existing 200mm AC gravity main with 250mm DI K9 pipe (4000 mts) and 90 mm PVC Rider main (4000 mts) from Nadapuram junction to Kakkamvellikkunnu GLSR
Status On-going
District Kozhikkode
Executing Office Vadakara PH Dn
AS Amount (Rs) 25910000
AS Number WRD005-130-PA-01
TS Amount (Rs) 25300000
TS Number CE/NR/KKD/9875/20-21
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 15000
Capacity in MLD 0.50
Actual Project Completion Date Date is not specified
Coverage Tuneri area
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB Project 6 - RWSS to Thuneri Village- Replacing existing 200mm AC gravity main with 250mm DI K9 pipe from Nadapuram junction to Kakkamvellikkunnu GLSR Purameri PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 Work cancelled at the risk and cost of original contractor. Work re tendered Purameri PH Sn - AE
13 May 2024 Work cancelled at the risk and cost of original contractor. Work re tendered Purameri PH Sn - AE
09 May 2024 Work cancelled at the risk and cost of original contractor. Work re tendered Purameri PH Sn - AE
06 May 2024 Work cancelled at the risk and cost of original contractor. Work re tendered Purameri PH Sn - AE
02 May 2024 24 Work cancelled at the risk and cost of original contractor. Work re tendered Purameri PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/09/2021
Scheduled date of Completion of the Project 31 Dec 2021
Expected date of Completion 31/05/2023

Processing Dates

AS Date 23 Mar 2019
TS Date 22 Oct 2020

Other details