Project | Supplying laying, testing and commissioning of 450mm (710 mtr) 300mm (1500mtr) and 250mm (1200mtr) DI K9 pipe from Kizhakkamabalam to Parakkode |
---|---|
Project Code | EKMGOK08135350P3 |
Type | Package |
Main Project | 19- Replacement of damaged ac pipes in vazhakkulam,kizhakkambalam & kunnathunadu panchayath |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Supplying laying, testing and commissioning of 450mm (710 mtr) 300mm (1500mtr) and 250mm (1200mtr) DI K9 pipe from Kizhakkamabalam to Parakkode |
Status | Completed |
District | Ernakulam |
Executing Office | Perumbavoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | |
TS Number | |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 27/06/2014 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 24/10/2016 |
AS Date | 03 Aug 2013 |
---|---|
TS Date | 20 Nov 2013 |
Estimate Approval | 20 Nov 2013 |
Tender Closing | 04 Feb 2014 |
Technichal Pre-Qualification | 07 Feb 2014 |
CE Approval | 28 Feb 2014 |
---|---|
Workorder Date | 01 Mar 2014 |
NA | 20 Mar 2014 |
Aluva AEE JJM |
Date: 25/11/2020 |
Work has been completed | 100% Completed
Work completed.