Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

UIDSSMT - Augmentation of WSS To Thalassery Municipality And Adjoining Town -Balance Work Of Construction Of OHSRChirakkakavu & Feeder Line To OHSRChirakkakavu - Package II-UIDSSMT -Augmentation of WSS To Thalassery Municipality OHSR Chirakkakavu BalanceWork-Pipeline Work

Project UIDSSMT - Augmentation of WSS To Thalassery Municipality And Adjoining Town -Balance Work Of Construction Of OHSRChirakkakavu & Feeder Line To OHSRChirakkakavu - Package II-UIDSSMT -Augmentation of WSS To Thalassery Municipality OHSR Chirakkakavu BalanceWork-Pipeline Work
Project Code KNRDEPO082012729
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description UIDSSMT - Augmentation of WSS To Thalassery Municipality And Adjoining Town -Balance Work Of Construction Of OHSRChirakkakavu & Feeder Line To OHSRChirakkakavu - Package II-UIDSSMT -Augmentation of WSS To Thalassery Municipality OHSR Chirakkakavu BalanceWork-Pipeline Work
Status On-going
District Kannur
Executing Office Kannur WS Dn
AS Amount (Rs) 17200000
AS Number E7-23296/06
TS Amount (Rs) 6400000
TS Number 5447/2022-2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 UIDSSMT - Augmentation of WSS To Thalassery Municipality And Adjoining Town -Balance Work Of Construction Of OHSRChirakkakavu & Feeder Line To OHSRChirakkakavu - Package II-UIDSSMT -Augmentation of WSS To Thalassery Municipality OHSR Chirakkakavu BalanceWork-Pipeline Work Thalassery PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Nov 2023 Final bill submitted Thalassery PH Sn AE
08 Nov 2023 Final bill submitted Thalassery PH Sn AE
03 Nov 2023 Final bill submitted Thalassery PH Sn AE
27 Oct 2023 Final bill submitted Thalassery PH Sn AE
20 Oct 2023 Final bill submitted Thalassery PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 09/06/2023

Processing Dates

AS Date 19 Aug 2022
TS Date 11 Nov 2022

Other details

Project Officers View