- Home
- DRW 2022- Replacement & Repair of Valves...
DRW 2022- Replacement & Repair of Valves - Replacing damaged valves in various places under PH section no. I & no.II kalpetta
| Project |
DRW 2022- Replacement & Repair of Valves - Replacing damaged valves in various places under PH section no. I & no.II kalpetta |
| Project Code |
WYDGOK032210316 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
DRW |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
DRW 2022- Replacement & Repair of Valves - Replacing damaged valves in various places under PH section no. I & no.II kalpetta |
| Status |
Short Closed |
| District |
Wayanad |
| Executing Office |
Kalpetta PH Sub Dn |
| AS Amount (Rs) |
500000
|
| AS Number |
3476/AEII(OP)/2020/KWA(II) |
| TS Amount (Rs) |
500000 |
| TS Number |
TS/2022-2023/2022/14402,TS/2022-2023/2022/14401 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
1000 |
| Capacity in MLD |
0.10 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Kalpetta |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DRW 2022 - Repair & replacement of valves - Replacing damaged valves in various places under PH section no. II Kalpetta |
Kalpetta PH Sn 2 |
|
| 2 |
DRW 2022 - Repair & replacement of valves - Replacing damaged valves in various places under PH section no. I Kalpetta |
Kalpetta PH Sn 1 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 01 Oct 2022 |
NOT TENDERED |
Kalpetta PH Sn 2 - AE |
|
| 17 Sep 2022 |
not tendered |
Kalpetta PH Sn 2 - AE |
|
| 14 Sep 2022 |
Tendered no offer received |
Kalpetta PH Sn 1 - AE |
|
| 30 Aug 2022 |
tendered no offer received
|
Sulthan Bathery PH Dn EE |
|
| 26 Aug 2022 |
Package 1 -Work Re tendered ,package 2- tendered No offer Received |
Sulthan Bathery PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
05/05/2022 |
| Scheduled date of Completion of the Project |
31 May 2022 |
| Expected date of Completion |
31/05/2022 |
Processing Dates
| AS Date |
29 Mar 2022 |
| TS Date |
21 Apr 2022 |