- Home
- Deposit - Dist.Panchayat - WSS to Pancha...
Deposit - Dist.Panchayat - WSS to Panchami-Kottatharavayal colony in Meppadi Grama Panchayath
Project |
Deposit - Dist.Panchayat - WSS to Panchami-Kottatharavayal colony in Meppadi Grama Panchayath |
Project Code |
WYDDEPO022313913 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit - Dist.Panchayat - WSS to Panchami-Kottatharavayal colony in Meppadi Grama Panchayath |
Status |
Completed |
District |
Wayanad |
Executing Office |
Kalpetta PH Sn 2 |
AS Amount (Rs) |
1109000
|
AS Number |
SC4-13/2022 |
TS Amount (Rs) |
1109000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/16031/2022_26_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
120 |
Capacity in MLD |
0.10 |
Actual Project Completion Date |
Date is not specified |
Coverage |
WSS to Panchami-Kottatharavayal colony |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit - Dist.Panchayat - WSS to Panchami-Kottatharavayal colony in Meppadi Grama Panchayath |
Kalpetta PH Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Mar 2024 |
Completed and Bill submitted |
Sulthan Bathery PH Dn EE |
|
26 Feb 2024 |
KSEB connection approved and work in progress. |
Kalpetta PH Sn 2 - AE |
|
23 Feb 2024 |
KSEB connection approved and work in progress. |
Kalpetta PH Sn 2 - AE |
|
19 Feb 2024 |
Waiting for KSEB connection approval. |
Kalpetta PH Sn 2 - AE |
|
14 Feb 2024 |
Waiting for KSEB connection approval. |
Kalpetta PH Sn 2 - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
05/04/2023 |
Scheduled date of Completion of the Project |
04 Jul 2023 |
Expected date of Completion |
31/01/2024 |
Processing Dates
AS Date |
23 Feb 2023 |
TS Date |
28 Feb 2023 |