Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT - Construction of 13 LL OHSR at Edakochi.

Project AMRUT - Construction of 13 LL OHSR at Edakochi.
Project Code EKMAMRUT1117877P2
Type Package
Main Project AMRUT - Construction of 13 LL OHSR at Edakochi.
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Construction of 13 LL OHSR at Edakochi.
Status On-going
District Ernakulam
Executing Office Kochi Project Division
Agreement Number
Agreement Date
TS Amount (Rs) 43000000
TS Number TS/CE/CR/KWA/60/17-18
Technical specification Design,Construction,testing,maintenance for a period of 18 months from the date of commissioning of 13LL OHSR as per the design & scope of work approved by Kerala Water Authority
Contractor Remani .S.Nair (Mob: 9562695880)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
20 Jan 2022 Pending Pending KWA-Organisational Project Risk Absence of officers in charge No comments available. Pending
01 Nov 2021 Pending 31 Jan 2022 Legal Project Risk After issuing termination notice for slow progress, the contractor obtained order from HC fro extension upto 31 Jan. The progress is too slow and work cannot be completed before the date No comments added. Action Taken
01 Nov 2021 Pending 31 Jan 2022 Contract Related Risks Hon'ble High Court of Kerala has extended the date of completion upto 31 Jan 2022. But the progress is very slow, cannot complete the work within the short extended period No comments added. Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/12/2018
Scheduled date of Completion as per agreement 30 Dec 2019
Expected date of Completion 31/12/2022

Processing Dates

TS Date 23 Jan 2018
Estimate Approval 23 Jan 2018
NIT Approval 20 Dec 2018
Tender Closing 22 Nov 2018
Price bid opening 26 Nov 2018

Approval Dates

Workorder Date 31 Dec 2018
NA 19 Jan 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kochi JNURM Projects AE-6
Date: 12/10/2022

Work in progress | 45% Completed

Edakochi OHSR, Concreting brace level concrete completed departmentally, Balance Work at the Risk and cost of original contractor retendered..

Kochi JNURM Projects AE-6
Date: 05/10/2022

Work in progress | 45% Completed

Edakochi OHSR: level 2 balance brace beams curing of concrete work on progress. .

Attached images

img