Project | AMRUT - Construction of 13 LL OHSR at Edakochi. |
---|---|
Project Code | EKMAMRUT1117877P2 |
Type | Package |
Main Project | AMRUT - Construction of 13 LL OHSR at Edakochi. |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | Construction of 13 LL OHSR at Edakochi. |
Status | On-going |
District | Ernakulam |
Executing Office | Kochi Project Division |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 43000000 |
TS Number | TS/CE/CR/KWA/60/17-18 |
Technical specification | Design,Construction,testing,maintenance for a period of 18 months from the date of commissioning of 13LL OHSR as per the design & scope of work approved by Kerala Water Authority |
Contractor | Remani .S.Nair (Mob: 9562695880) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
20 Jan 2022 | Pending | Pending | KWA-Organisational Project Risk | Absence of officers in charge | No comments available. | Pending |
01 Nov 2021 | Pending | 31 Jan 2022 | Legal Project Risk | After issuing termination notice for slow progress, the contractor obtained order from HC fro extension upto 31 Jan. The progress is too slow and work cannot be completed before the date | No comments added. | Action Taken |
01 Nov 2021 | Pending | 31 Jan 2022 | Contract Related Risks | Hon'ble High Court of Kerala has extended the date of completion upto 31 Jan 2022. But the progress is very slow, cannot complete the work within the short extended period | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 31/12/2018 |
---|---|
Scheduled date of Completion as per agreement | 30 Dec 2019 |
Expected date of Completion | 31/12/2022 |
TS Date | 23 Jan 2018 |
---|---|
Estimate Approval | 23 Jan 2018 |
NIT Approval | 20 Dec 2018 |
Tender Closing | 22 Nov 2018 |
Price bid opening | 26 Nov 2018 |
Workorder Date | 31 Dec 2018 |
---|---|
NA | 19 Jan 2019 |
Kochi JNURM Projects AE-6 |
Date: 12/10/2022 |
Work in progress | 45% Completed
Edakochi OHSR, Concreting brace level concrete completed departmentally, Balance Work at the Risk and cost of original contractor retendered..