Standardization of Electrical Installation of 315 KVA Sub station at Kannamoola Pump House.
Project |
Standardization of Electrical Installation of 315 KVA Sub station at Kannamoola Pump House. |
Project Code |
TVMGOK012211921 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Standardization of Electrical Installation of 315 KVA Sub station at Kannamoola Pump House. |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Plamoodu project Sn |
AS Amount (Rs) |
965000
|
AS Number |
KWA/JB/PIU1/AE1/12/2021 |
TS Amount (Rs) |
774973 |
TS Number |
TS/2021-2022/2021/15855 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
0.50 |
Actual Project Completion Date |
29 Oct 2022 |
Coverage |
Kannamoola |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
TSS-Standardization of electrical installation of 315 KVA substation at Kannammoola pump house |
Plamoodu project Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Oct 2022 |
Work has been completed |
Plamoodu Sewerage Project Sn AE |
|
29 Oct 2022 |
Work has been completed |
Plamoodu Sewerage Project Sn AE |
|
27 Oct 2022 |
Panel board installation work is in progress. |
Plamoodu Sewerage Project Sn AE |
|
25 Oct 2022 |
Panel board installation work is in progress. |
Plamoodu Sewerage Project Sn AE |
|
23 Oct 2022 |
Panel board installation work started |
Plamoodu Sewerage Project Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/07/2022 |
Scheduled date of Completion of the Project |
12 Oct 2022 |
Expected date of Completion |
12/12/2022 |
Processing Dates
AS Date |
31 Jan 2022 |
TS Date |
16 Feb 2022 |