CARWSS to Kozhinjampara and adjoining villages - Pipe replacement project - Existing 300mm AC with 500mm DI K9 Raw Water Pumping main (6500m)
Project |
CARWSS to Kozhinjampara and adjoining villages - Pipe replacement project - Existing 300mm AC with 500mm DI K9 Raw Water Pumping main (6500m) |
Project Code |
PKDGOK09176712 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
CARWSS to Kozhinjampara and adjoining villages - Pipe replacement project - Existing 300mm AC with 500mm DI K9 Raw Water Pumping main (6500m) |
Status |
Completed |
District |
Palakkad |
Executing Office |
Palakkad PH Dn |
AS Amount (Rs) |
75000000
|
AS Number |
GO(Rt)No 800/2017/WRD |
TS Amount (Rs) |
75000000 |
TS Number |
KWA/CE/NR/26/17-18 |
Total Bill Submitted (Rs) |
59459000 |
Total Bill Paid (Rs) |
59459000 |
Population Benefitted |
20000 |
Capacity in MLD |
5.00 |
Actual Project Completion Date |
08 Nov 2018 |
Coverage |
kOZHINJMPARA, ERUTHENPATHY, VADAKARAPATHY PANCHAYATHS |
Packages
No. |
Project Name |
Location |
View |
1 |
CARWSS to Kozhinjampara and adjoining villages - Pipe replacement project - Existing 300mm AC with 500mm DI K9 Raw Water Pumping main (6500m) |
Palakkad PH Dn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/03/2018 |
Scheduled date of Completion of the Project |
29 Nov 2018 |
Expected date of Completion |
29/11/2018 |
Processing Dates
AS Date |
28 Sep 2017 |
TS Date |
13 Dec 2017 |