Project | AMRUT 2015-16- THIRUVANANTHAPURAM SEWERAGE- SAAP |
---|---|
Project Code | TVMAMRUT0217913 |
Type | Main project |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | TSS- D Block Zone II -Supplying,conveying Laying and jointing 700 mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam-Kannammoola Ch.952m to 1334m TSS- D Block Zone II -Supplying,conveying Laying and jointing 700 mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam-Kannammoola Ch.1334m to1728m |
Status | Completed |
District | Thiruvananthapuram |
Executing Office | Plamoodu project Sn |
AS Amount (Rs) | 16400000 |
AS Number | GO(Rt).NO 534/2017/LSGD dt 23/02/2017, 1938/2020/LSGD dt 16/10/2020 |
TS Amount (Rs) | 13308000 |
TS Number | 5551/2019-20 dtd 18.11.2019 of CESR |
Total Bill Submitted (Rs) | 0 |
Total Bill Paid (Rs) | 0 |
Population Benefitted | 15000 |
Capacity in MLD | 4.00 |
Actual Project Completion Date | 31 Dec 2021 |
Coverage | TSS- D Block Zone II -Supplying,conveying Laying and jointing 700 mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam-Kannammoola Ch.952m to 1334m TSS- D Block Zone II -Supplying,conveying Laying and jointing 700 mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam-Kannammoola Ch.1334m to1728m |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | TSS- D Block Zone II -Supplying,conveying Laying and jointing 700 mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam-Kannammoola Ch.952m to 1334m 2 TSS- D Block Zone II -Supplying,conveying Laying and jointing 700 mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam-Kannammoola Ch.1334m to1728m | Plamoodu project Sn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Feb 2022 | All work completed. | Plamoodu Sewerage Project Sn AE | |
21 Feb 2022 | All work completed. | Plamoodu Sewerage Project Sn AE | |
19 Feb 2022 | All work completed . | Plamoodu Sewerage Project Sn AE | |
16 Feb 2022 | All work completed . | Plamoodu Sewerage Project Sn AE | |
14 Feb 2022 | All work completed . | Plamoodu Sewerage Project Sn AE |
Date of start of Project | 30/10/2020 |
---|---|
Scheduled date of Completion of the Project | 13 Apr 2021 |
Expected date of Completion | 31/12/2021 |
AS Date | 16 Oct 2020 |
---|---|
TS Date | 19 Dec 2017 |
Project Officers | View |
---|