State plan 2022-23 Replacing 80mm, 100mm, 150mm AC pipe line in various places in Vadakara Municipality

Project State plan 2022-23 Replacing 80mm, 100mm, 150mm AC pipe line in various places in Vadakara Municipality
Project Code CLTGOK052211384
Type Main project
Funding Agency GOK
Category Replacement of Pipe lines
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State plan 2022-23 Replacing 80mm, 100mm, 150mm AC pipe line in various places in Vadakara Municipality
Status On-going
District Kozhikkode
Executing Office Vadakara WSP Sub Dn
AS Amount (Rs) 4500000
AS Number 11943/AE 2/2022/KWA ( 1 )
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 31 Mar 2024
Coverage Vadakara Municipality (Partial )

Packages

No. Project Name Location View
1 State plan 2022-23 Replacing 80mm, 100mm, 150mm AC pipe line in various places in Vadakara Municipality Vadakara WSP Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Dec 2023 road reformation to be done Vatakara PH Sn - AE
13 Nov 2023 road reformation to be done Vatakara PH Sn - AE
31 Oct 2023 road reformation to be done Vatakara PH Sn - AE
25 Oct 2023 road reformation to be done Vatakara PH Sn - AE
13 Oct 2023 road reformation to be taken Vatakara PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 30/04/2024

Processing Dates

AS Date 18 May 2022