DEPOSIT-Kochi Corporation-Laying 75mm, 63mm PVC pipe line ( 6Kg/cm2) by the side wall of Kureethode ( Mannarakkara road) in div 47 ( new) ( old 33)-Pipeline Work

Project DEPOSIT-Kochi Corporation-Laying 75mm, 63mm PVC pipe line ( 6Kg/cm2) by the side wall of Kureethode ( Mannarakkara road) in div 47 ( new) ( old 33)-Pipeline Work
Project Code EKMDEPO022315733P1
Type Package
Main Project DEPOSIT-Kochi Corporation-Laying 75mm, 63mm PVC pipe line ( 6Kg/cm2) by the side wall of Kureethode ( Mannarakkara road) in div 47 ( new) ( old 33)-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Kochi Corporation-Laying 75mm, 63mm PVC pipe line ( 6Kg/cm2) by the side wall of Kureethode ( Mannarakkara road) in div 47 ( new) ( old 33)-Pipeline Work
Status On-going
District Ernakulam
Executing Office Vytilla Section 1
Agreement Number
Agreement Date
TS Amount (Rs) 1161000
TS Number DEPOSIT-Kochi Corporation-Laying 75mm, 63mm PVC pipe line ( 6Kg/cm2) by the side wall of Kureethode ( Mannarakkara road) in div 47 ( new) ( old 33)-Pipeline Work
Technical specification DEPOSIT-Kochi Corporation-Laying 75mm, 63mm PVC pipe line ( 6Kg/cm2) by the side wall of Kureethode ( Mannarakkara road) in div 47 ( new) ( old 33)-Pipeline Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/03/2024
Scheduled date of Completion as per agreement 05 Apr 2024
Expected date of Completion 05/04/2024

Processing Dates

TS Date 07 Jun 2023
Estimate Approval 07 Jun 2023
NIT Approval 07 Jul 2023
Tender Closing 25 Jul 2023
Technichal Pre-Qualification 26 Jul 2023
Price bid opening 26 Jul 2023

Approval Dates

Workorder Date 16 Dec 2023
NA 29 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vytilla Section AE - 1
Date: 30/04/2024

Work has been completed | 100% Completed

House connection shifting completed . work completed.

Vytilla Section AE - 1
Date: 18/04/2024

Work in progress | 60% Completed

Laying of 63mm PVC pipe completed.