Jal Jeevan Mission (JJM)-Kannur District-Kolachery Panchayath - WSS to Kolachery and adjoining Panchayaths - Phase III - Reappropriation work- Laying distribution system and providing FHTCs -Pipeline Work

Project Jal Jeevan Mission (JJM)-Kannur District-Kolachery Panchayath - WSS to Kolachery and adjoining Panchayaths - Phase III - Reappropriation work- Laying distribution system and providing FHTCs -Pipeline Work
Project Code KNRJJM102316033
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-Kannur District-Kolachery Panchayath - WSS to Kolachery and adjoining Panchayaths - Phase III - Reappropriation work- Laying distribution system and providing FHTCs -Pipeline Work
Status On-going
District Kannur
Executing Office Kolachery PH Sn
AS Amount (Rs) 137000000
AS Number G.O.(Rt)No.897/2023/WRD Dated,Thiruvananthapuram, 26-10-2023
TS Amount (Rs) 129400000
TS Number 22467/2023-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Kannur District-Kolachery Panchayath - WSS to Kolachery and adjoining Panchayaths - Phase III - Re appropriation work- Laying distribution system and providing FHTCs -Pipeline Work Kolachery PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Jul 2025 140 mm 10 Kg/cm2 - 329.5 m ,110 mm 10 Kg/Cm2- 2188 m, 90 mm 10 Kg/Cm2-3334.5 m, 75 mm 10 Kg/Cm2- 2643 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 81 Nos Kolachery PH Sn AE
24 Jun 2025 140 mm 10 Kg/cm2 - 329.5 m ,110 mm 10 Kg/Cm2- 2188 m, 90 mm 10 Kg/Cm2-3334.5 m, 75 mm 10 Kg/Cm2- 2643 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 61 Nos Kolachery PH Sn AE
17 Jun 2025 140 mm 10 Kg/cm2 - 329.5 m ,110 mm 10 Kg/Cm2- 2188 m, 90 mm 10 Kg/Cm2-3334.5 m, 75 mm 10 Kg/Cm2- 2643 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 61 Nos Kolachery PH Sn AE
11 Jun 2025 140 mm 10 Kg/cm2 - 329.5 m ,110 mm 10 Kg/Cm2- 2188 m, 90 mm 10 Kg/Cm2-3334.5 m, 75 mm 10 Kg/Cm2- 2643 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 61 Nos Kolachery PH Sn AE
03 Jun 2025 140 mm 10 Kg/cm2 - 329.5 m ,110 mm 10 Kg/Cm2- 2188 m, 90 mm 10 Kg/Cm2-3334.5 m, 75 mm 10 Kg/Cm2- 2643 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 59 Nos Kolachery PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 26 Oct 2023
TS Date 21 Dec 2023

Other details

Project Officers View