Amrut - 2016-17-Thrissur corporation-Strengthening the exisiting distribution system to Thrissur Corporation area - Replacement of very old 80/100/125/300 AC and 700mm PREMO pipes with 110/140 PVC and 200/300/350mm DI pipes at varoius places in Thrissur Corporation .14.4 C
Project |
Amrut - 2016-17-Thrissur corporation-Strengthening the exisiting distribution system to Thrissur Corporation area - Replacement of very old 80/100/125/300 AC and 700mm PREMO pipes with 110/140 PVC and 200/300/350mm DI pipes at varoius places in Thrissur Corporation .14.4 C |
Project Code |
TCRAMRUT02171079 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
1)350 MM DI K9-1071 M
2) 300 MM DI K9-479 M
3) 250 MM DI K9-500 M
4)200 mmDI K9-9156.5 M
5)160 mm PVC-23634 M |
Status |
Completed |
District |
Thrissur |
Executing Office |
Thrissur PH Dn |
AS Amount (Rs) |
144000000
|
AS Number |
GO(Rt) No.534/17/LSGD |
TS Amount (Rs) |
144000000 |
TS Number |
AMRUT/TEC/NR/07/2017 |
Total Bill Submitted (Rs) |
76612400 |
Total Bill Paid (Rs) |
76612400 |
Population Benefitted |
15000 |
Capacity in MLD |
36.00 |
Actual Project Completion Date |
24 Jan 2022 |
Coverage |
Thrissur corporation , |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Amruth -Strengthening the exisiting distribution system to Thrissur Corporation area - Replacement of very old 80/100/125/300 AC and 700mm PREMO pipes with 110/140 PVC and 200/300/350mm DI pipes at varoius places in Thrissur Corporation . |
Thrissur WW Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Jan 2023 |
Final bill of main work submitted to Thrissur Corporation on 29/10/2022.
|
Thrissur PH Dn EE |
|
27 Jan 2022 |
Work Completed, Final bill under preparation |
Thrissur PH Dn EE |
|
18 Jan 2022 |
Work completed on 15-01-2022 |
Thrissur WW Sn - AE 1 |
|
18 Jan 2022 |
Work completed |
Thrissur WW Sn - AE 1 |
|
11 Jan 2022 |
Inter connection and connection shifting work in progres |
Thrissur WW Sn - AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/08/2018 |
Scheduled date of Completion of the Project |
01 Aug 2019 |
Expected date of Completion |
15/01/2022 |
Processing Dates
AS Date |
23 Feb 2017 |
TS Date |
05 Jun 2017 |