Construction of 5.00L.L. O.H.S.R. Providing Balance FHTCs, at Thoppilpara, Renovation of Pochakkonam Chira, Providing and Fixing Pressure Filter, Pumping Main and Interconnections in Ezhukone for improving water supply in Ezhukone Grama Panchayat (Balance Work )

Project Construction of 5.00L.L. O.H.S.R. Providing Balance FHTCs, at Thoppilpara, Renovation of Pochakkonam Chira, Providing and Fixing Pressure Filter, Pumping Main and Interconnections in Ezhukone for improving water supply in Ezhukone Grama Panchayat (Balance Work )
Project Code KLMJJM082315467
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Construction of 5.00L.L. O.H.S.R. Providing Balance FHTCs, at Thoppilpara, Renovation of Pochakkonam Chira, Providing and Fixing Pressure Filter, Pumping Main and Interconnections in Ezhukone for improving water supply in Ezhukone Grama Panchayat (Balance Work )
Status On-going
District Kollam
Executing Office Kottarakkara PH Dn
AS Amount (Rs) 210640000
AS Number 541/2020/WRD
TS Amount (Rs) 26499000
TS Number 9098/2023-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
No Packages has been added for this project.

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Apr 2024 Work in progress Kottarakkara PH Sn - AE
27 Apr 2024 Work in progress Kottarakkara PH Sn - AE
22 Apr 2024 work in progress Kottarakkara PH Sn - AE
20 Apr 2024 Column water curing... Kottarakkara PH Sn - AE
19 Apr 2024 First floor column concert.. Kottarakkara PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/11/2023
Scheduled date of Completion of the Project 01 Nov 2024
Expected date of Completion 01/11/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 16 Jul 2023

Other details