Project | AMRUT - Kannur Corporation - Laying gravity main from WSS to Kannur at Melechovva to sump at Avera to OHSR at Thottada inlcuding erection of pump set at Avera in Kannur Corporation-Package I. |
---|---|
Project Code | KNRAMRUT08172771P1 |
Type | Package |
Main Project | AMRUT - Kannur Corporation - Laying gravity main from WSS to Kannur at Melechovva to sump at Avera to OHSR at Thottada inlcuding erection of pump set at Avera in Kannur Corporation |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | Laying gravity main from WSS to Kannur at Melechovva to sump at Avera to OHSR at Thottada inlcuding erection of pump set at Avera in Kannur Corporation. |
Status | On-going |
District | Kannur |
Executing Office | Koothuparamba Project Sn No2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 65000000 |
TS Number | KWA/CE/NR/18/2017-18 dated 24/10/2017 |
Technical specification | Laying 350 mm DI gravity main(2630 m) from OHSR Melechovva to GL Sump At Avera and Laying Puming Main From sump at Avera to Proposed OHSR at Thottada includingsupply and erection of 2 nos 70 HP pumpsets |
Contractor | Sohail shamsudheen (Mob: 9809509114) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 03/02/2018 |
---|---|
Scheduled date of Completion as per agreement | 30 Jan 2019 |
Expected date of Completion | 31/12/2021 |
TS Date | 24 Oct 2017 |
---|---|
Estimate Approval | 24 Oct 2017 |
NIT Approval | 15 Nov 2017 |
Tender Closing | 30 Nov 2017 |
Technichal Pre-Qualification | 18 Dec 2017 |
Price bid opening | 18 Dec 2017 |
Workorder Date | 31 Jan 2018 |
---|---|
NA | 28 Feb 2018 |
Koothuparamba Proj AE 2 |
Date: 26/05/2022 |
Work has been completed | 100% Completed
completed and commissioned.Final bill paid.
Koothuparamba Proj AE 2 |
Date: 22/04/2022 |
Work has been completed | 100% Completed
Work completed on 14/03/22.Final bill submitted.