AMRUT - Kannur Corporation - Laying gravity main from WSS to Kannur at Melechovva to sump at Avera to OHSR at Thottada inlcuding erection of pump set at Avera in Kannur Corporation-Package I.

Project AMRUT - Kannur Corporation - Laying gravity main from WSS to Kannur at Melechovva to sump at Avera to OHSR at Thottada inlcuding erection of pump set at Avera in Kannur Corporation-Package I.
Project Code KNRAMRUT08172771P1
Type Package
Main Project AMRUT - Kannur Corporation - Laying gravity main from WSS to Kannur at Melechovva to sump at Avera to OHSR at Thottada inlcuding erection of pump set at Avera in Kannur Corporation
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Laying gravity main from WSS to Kannur at Melechovva to sump at Avera to OHSR at Thottada inlcuding erection of pump set at Avera in Kannur Corporation.
Status On-going
District Kannur
Executing Office Koothuparamba Project Sn No2
Agreement Number
Agreement Date
TS Amount (Rs) 65000000
TS Number KWA/CE/NR/18/2017-18 dated 24/10/2017
Technical specification Laying 350 mm DI gravity main(2630 m) from OHSR Melechovva to GL Sump At Avera and Laying Puming Main From sump at Avera to Proposed OHSR at Thottada includingsupply and erection of 2 nos 70 HP pumpsets
Contractor Sohail shamsudheen (Mob: 9809509114)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/02/2018
Scheduled date of Completion as per agreement 30 Jan 2019
Expected date of Completion 31/12/2021

Processing Dates

TS Date 24 Oct 2017
Estimate Approval 24 Oct 2017
NIT Approval 15 Nov 2017
Tender Closing 30 Nov 2017
Technichal Pre-Qualification 18 Dec 2017
Price bid opening 18 Dec 2017

Approval Dates

Workorder Date 31 Jan 2018
NA 28 Feb 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparamba Proj AE 2
Date: 26/05/2022

Work has been completed | 100% Completed

completed and commissioned.Final bill paid.

Koothuparamba Proj AE 2
Date: 22/04/2022

Work has been completed | 100% Completed

Work completed on 14/03/22.Final bill submitted.