Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB- WSS to Chazhoor, Thanniyam and Anthikkad Panchayath in Thrissur District

Project KIIFB- WSS to Chazhoor, Thanniyam and Anthikkad Panchayath in Thrissur District
Project Code TCRKIIFB1118516
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB 2017-18 - WSS to Chazhoor, Thanniyam and Anthikkad Panchayath in Thrissur District with Package 1 -a) Renovation of Well cum pumphouse- Illikkal and Kolothumkadav b) 250mm DI RWPM-1100M (From Kolothumkadav) c) 12MLD at Chazhoor d) Pressure filter e)Raw water pumpset-100HP-2 Nos, 35HP-2Nos f) Clearwater pumpset - 70HP 2Nos, 30HP 2Nos g)250 KVA Transformer - 1nos h) SCADA I) 12LL OHSR Construction of 5.5 LL Sump cum Pump house & Package 2 a) 11LL OHSR at Thanniam b) 8.6LL OHSR at Anthikad c) 400mm DI K9 CWPM-4350m d) 300mm DI K9 CWPM-6090m
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 347600000
AS Number WRD025-02-PA-01
TS Amount (Rs) 344000000
TS Number TS/2019-20/2019/12560 TS/2019-20/2019/12563
Total Bill Submitted (Rs) 154405165
Total Bill Paid (Rs) 154405165
Population Benefitted 96969
Capacity in MLD 12.00
Actual Project Completion Date 24 Aug 2021
Coverage Chazhoor, Thanniyam and Anthikkad Panchayath in Thrissur District
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB- WSS to Chazhoor, Thanniyam and Anthikkad Panchayath in Thrissur District - Package 1 Nattika Project Dn
2 KIIFB- WSS to Chazhoor, Thanniyam and Anthikkad Panchayath in Thrissur District-Package 2 Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 May 2024 Package 1:wash water tank roof slab reinforcement and brace beam shuttering work, first floor brick work , aerator tiling work and interconnection work at illikkal pump house ongoing. Sump, aerator plastering and Clariflocculator, Office and lobby area roof slab ,beam, stair concrete work are completed. Raw water pumping main road restoration completed. Package 2 -10 km clear water pumping main laying completed . Painting & compound wall construction completed respectively at Anthikad & Thanniyam OHSR site. Lightening arrestor work completed at Thanniyam OHSR. Lettering work completed .90% road restoration completed. Nattika Project Dn AE 2
17 May 2024 Package 1:wash water tank roof slab reinforcement and shuttering work, first floor brick work and interconnection work at illikkal pump house ongoing. Sump, aerator plastering and Clariflocculator, Office and lobby area roof slab ,beam, stair concrete work are completed. Raw water pumping main road restoration completed. Package 2 -10 km clear water pumping main laying completed . Painting & compound wall construction completed respectively at Anthikad & Thanniyam OHSR site. Lightening arrestor work completed at Thanniyam OHSR. Lettering work completed .90% road restoration completed. Nattika Project Dn AE 2
16 May 2024 Package 1:wash water tank roof slab reinforcement work, first floor brick work and interconnection work at illikkal pump house ongoing. Sump, aerator plastering and Clariflocculator, Office and lobby area roof slab ,beam, stair concrete work are completed. Raw water pumping main road restoration completed. Package 2 -10 km clear water pumping main laying completed . Painting & compound wall construction completed respectively at Anthikad & Thanniyam OHSR site. Lightening arrestor work completed at Thanniyam OHSR. Lettering work completed .90% road restoration completed. Nattika Project Dn AE 2
15 May 2024 Package 1:Brace beam shuttering works, first floor brick work and interconnection work at illikkal pump house ongoing. Sump, aerator plastering and Clariflocculator, Office and lobby area roof slab ,beam, stair concrete work are completed. Raw water pumping main road restoration completed. Package 2 -10 km clear water pumping main laying completed . Painting & compound wall construction completed respectively at Anthikad & Thanniyam OHSR site. Lightening arrestor work completed at Thanniyam OHSR. Lettering work completed .90% road restoration completed. Nattika Project Dn AE 2
14 May 2024 Package 1:Brace beam shuttering works, first floor brick work ongoing. Sump, aerator plastering and Clariflocculator, Office and lobby area roof slab ,beam, stair concrete work are completed. Raw water pumping main road restoration completed. Package 2 -10 km clear water pumping main laying completed . Painting & compound wall construction completed respectively at Anthikad & Thanniyam OHSR site. Lightening arrestor work completed at Thanniyam OHSR. Lettering work completed .90% road restoration completed. Nattika Project Dn AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 30/07/2020
Scheduled date of Completion of the Project 24 Aug 2021
Expected date of Completion 31/12/2023

Processing Dates

AS Date 13 Nov 2018
TS Date 31 Aug 2019

Other details

Project Officers View