- Home
- Water supply improvements to Mynagappall...
Water supply improvements to Mynagappally- Phase I- S/L clear water 200mm and 300mm DI K9 pumping main from sasthamkottah WTP to ICS OHSR and Public Market OHSR at Mynagappally, Construction of 15.2 LL OHSR at Public Market compound, S/E of 40HP( one stand by) clear water pump and motor , additional power allocation to KSEB, interconnection works at TP site solar and automation charges, road restoration charges and LS provision for demolishing old Anganvadi building and similar works
Project |
Water supply improvements to Mynagappally- Phase I- S/L clear water 200mm and 300mm DI K9 pumping main from sasthamkottah WTP to ICS OHSR and Public Market OHSR at Mynagappally, Construction of 15.2 LL OHSR at Public Market compound, S/E of 40HP( one stand by) clear water pump and motor , additional power allocation to KSEB, interconnection works at TP site solar and automation charges, road restoration charges and LS provision for demolishing old Anganvadi building and similar works |
Project Code |
KLMGOK11194404 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Water supply improvements to Mynagappally- Phase I- S/L clear water 200mm and 300mm DI K9 pumping main from sasthamkottah WTP to ICS OHSR and Public Market OHSR at Mynagappally, Construction of 15.2 LL OHSR at Public Market compound, S/E of 40HP( one stand by) clear water pump and motor , additional power allocation to KSEB, interconnection works at TP site solar and automation charges, road restoration charges and LS provision for demolishing old Anganvadi building and similar works |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
51000000
|
AS Number |
GORT 797/2019 WRD GoK dated 5.11.19 |
TS Amount (Rs) |
48840000 |
TS Number |
2625/2020-21 |
Total Bill Submitted (Rs) |
5919827 |
Total Bill Paid (Rs) |
5531400 |
Population Benefitted |
15000 |
Capacity in MLD |
1.52 |
Actual Project Completion Date |
23 Sep 2022 |
Coverage |
30%of work completed |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Water supply improvements to Mynagappally- Phase I- S/L clear water 200mm and 300mm DI K9 pumping main from sasthamkottah WTP to ICS OHSR and Public Market OHSR at Mynagappally, Construction of 15.2 LL OHSR at Public Market compound, S/E of 40HP( one stand by) clear water pump and motor , additional power allocation to KSEB, interconnection works at TP site solar and automation charges, road restoration charges and LS provision for demolishing old Anganvadi building and similar works |
Kollam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Aug 2022 |
Finishing work is in progress |
Kollam Project HD |
|
01 Jun 2022 |
Package 1 is nearing completion ,painting plastering and handrail work is in progress |
Kollam Project HD |
|
11 May 2022 |
Work in progress. Curing and Plastering of projection and outside beam is in progress. |
Kollam Project HD |
|
18 Apr 2022 |
Vertical pipe connection completed .concrete side wall of water tank completed . Plastering of OHSR is progressing. Handrail work of staircase is progressing . Solar panel installation completed. KSEB grid connection is on progress. Pump erection at Sasthamcotta WTP is progressing |
Kollam Project HD |
|
26 Feb 2022 |
Work in progress. Reinforcement work of roof slab in progress . Solar panel installation work starting at Sasthamcotta WTP and form work for Floor beam is starting.
|
Kollam Project HD |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
24/12/2020 |
Scheduled date of Completion of the Project |
23 May 2022 |
Expected date of Completion |
31/08/2022 |
Processing Dates
AS Date |
15 Nov 2019 |
TS Date |
25 Jun 2020 |