State plan-2018-19-Painting of Peppara Dam, shutters, Valve house, pump house and balance Repair works of Damaged Handrails of Peppara Dam
Project |
State plan-2018-19-Painting of Peppara Dam, shutters, Valve house, pump house and balance Repair works of Damaged Handrails of Peppara Dam |
Project Code |
TVMGOK08184495 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State plan-2018-19-Painting of Peppara Dam, shutters, Valve house, pump house and balance Repair works of Damaged Handrails of Peppara Dam |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Aruvikkara Sn 4 |
AS Amount (Rs) |
1690000
|
AS Number |
AS/2018/4850 |
TS Amount (Rs) |
1690000 |
TS Number |
3478/2018-19 |
Total Bill Submitted (Rs) |
1665148 |
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
25 Nov 2020 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
State plan-2018-19-Painting of Peppara Dam, shutters, Valve house, pump house and balance Repair works of Damaged Handrails of Peppara Dam |
Aruvikkara HW Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Nov 2020 |
Completed |
Aruvikkara HW Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/02/2019 |
Scheduled date of Completion of the Project |
25 Feb 2020 |
Expected date of Completion |
25/11/2020 |
Processing Dates
AS Date |
20 Aug 2018 |
TS Date |
15 Dec 2018 |